Figure 29. Packaging for fascia
1
4U fascia (front)
2
1U fascia (power supply units)
fascia: 2077-92F ” on page 66.
13. Install the drives, as described in “Installing or replacing a drive: 2077-92F ” on page 59.
14. Replace the top cover, as described in “Installing or replacing the top cover: 2077-92F ” on page
15. Lower the mechanical lift so that you can remove the remaining foam blocks away from the
expansion enclosure.
16. Slide the latch on the side of each rail and push the expansion enclosure securely into the rack, as
described in steps “3” on page 48 through “5” on page 48 in “Installing or replacing an expansion
enclosure in a rack: 2077-92F ” on page 47.
17. Remove the cable management arm assembly from its packaging (
2
18. Attach the cable management arm, as described in “Installing or replacing the cable-management
19. Connect the SAS cables, as described in “Removing and installing a SAS cable: 2077-92F ” on page
20. Connect the power cables.
Removing the top cover: 2077-92F
To complete some service tasks, you might need to remove the top cover from a 2077-92F expansion
enclosure.
Before you begin
Important: You can remove the cover without powering off the expansion enclosure. However, to
maintain operating temperature, replace the cover within 15 minutes of its removal. When the cover is
removed, the reduction in airflow through the enclosure might cause the enclosure or its components to
shut down to protect from overheating.
42 Storwize V5000 Gen2: Quick Installation Guide
Summary of Contents for Storwize V5000 Gen2
Page 1: ...IBM Storwize V5000 Gen2 Quick Installation Guide IBM...
Page 5: ...Index 149 v...
Page 6: ...vi...
Page 156: ...130 Storwize V5000 Gen2 Quick Installation Guide...
Page 164: ...138 Storwize V5000 Gen2 Quick Installation Guide...
Page 166: ...140 Storwize V5000 Gen2 Quick Installation Guide...
Page 168: ...142 Storwize V5000 Gen2 Quick Installation Guide...
Page 177: ......
Page 178: ...IBM...