6. Make sure required host system updates are installed.
7. Begin installing and testing the Advanced Function Presentation licensed
programs and updates on the host system.
Step Three–Review Progress of Site Preparation
1. Review site-preparation progress with the IBM installation planning
representative.
2. Make sure the electrical wiring and outlets are being installed on schedule.
3. Make sure the attachment lines and equipment are being installed on
schedule.
Step Four–Make sure Site Preparation is Complete
1. Make sure installation and testing of electrical wiring and outlet is complete.
2. Make sure all site preparation activity is complete.
3. Gather information for the configuration worksheets in Chapter 5,
“Configuring the Printer and Its Attachments” on page 23, and schedule an
NCP Generation if needed.
Important
Before the customer engineer can install the printer you must complete
a configuration worksheet for the attachments you plan to use.
Completing the attachment worksheets usually requires input from the
personnel responsible for network and device driver configuration.
Simplified versions of these worksheets are available in this book (see
“System Attachment Worksheets” on page 24). However, for detailed
worksheets, instructions, and examples, please refer to the
IBM
InfoPrint 60; 3130, 3160, and 3935 Advanced Function Printers:
Attachment Configuration Handbook, S544-3977. If you do not have a
copy of the handbook, ask your marketing representative to obtain one
for you.
Step Five–Arrival of the 3160
1. Contact the customer engineer and arrange to have the printer installed.
2. Arrange to have the printer attached to the host system.
3. Complete tests of the Advanced Function Presentation licensed programs,
including the IBM-supplied installation verification procedures.
Chapter 2. Planning Overview
9
Summary of Contents for 3160
Page 1: ...InfoPrint 60 3160 Advanced Function Printer IBM Introduction and Planning Guide G544 5242 03...
Page 2: ......
Page 3: ...InfoPrint 60 3160 Advanced Function Printer IBM Introduction and Planning Guide G544 5242 03...
Page 7: ...Acronyms and Abbreviations 79 Index 81 Contents v...
Page 10: ...viii InfoPrint 60 and 3160 Introduction and Planning Guide...
Page 36: ...22 InfoPrint 60 and 3160 Introduction and Planning Guide...
Page 52: ...38 InfoPrint 60 and 3160 Introduction and Planning Guide...
Page 82: ...68 InfoPrint 60 and 3160 Introduction and Planning Guide...
Page 94: ...80 InfoPrint 60 and 3160 Introduction and Planning Guide...
Page 98: ...84 InfoPrint 60 and 3160 Introduction and Planning Guide...
Page 101: ......