INSTALLING LOWER FRONT PANELS
The lower front panels are shipped inside each
merchandiser.
A
FTER
merchandisers have been
leveled and joined, and all drip piping, electrical
and refrigeration work has been completed,
install the lower front panel.
To Install Lower Front Panel
1. The lower front panel supports are designed
to fit into the slots on the top of the lower
front panel.
2. Once the top is positioned, lift the panel up
and drop it over the tabs on the front close-off
brackets.
Space between the Lower Front Panel and the
floor may be covered using a vinyl cove base
trim (field supplied). The size of trim needed will
depend on how much the floor is out of level.
To install the trim to the front panel:
1. Remove all dirt, wax and grease from the area
of the lower front panel where adhesion will
be necessary. This is to ensure a good and
secure installation.
2. Apply a good contact cement to the cove trim
and allow proper drying time according to the
directions supplied with the cement.
3. Install the trim on the lower front panel so
that it is lying flush with the floor. D
O NOT
SEAL THE TRIM TO THE FLOOR
.
4.
If required by local health codes
the Cove
Trim may be sealed to the floor, using a sili-
cone type sealer. Sealant must be removed
and replaced when servicing.
Lower Front Panel
Front Close-off Bracket
Lower Front Panel Support
Contact
Cement
Cove Trim