Description
The pneumatically operated LH-224 is a
lightweight, high speed Installation Tool
designed to install Huck blind and two
piece Fasteners up to 6.35 mm (1/4")
diameter. Pulling action of the piston is
provided by a pneumatic- hydraulic
intensifier system powered by 6.2 to 6.9
bar (90 to 100 psi) air pressure. The
correct Nose Assembly must be fitted to
the Installation Tool to suit the particular
Huck fastener being used.
The fastener installation sequence starts
when the Tool trigger is operated and the
return cycle
starts when the trigger is released. The
Tool piston is returned to the fully forward
position by a compresssion spring in the
head of the tool at the completion of the
fastener installation cycle.
Intended Use
The LH-224 hand held Installation Tool is
designed to be used in a normal, factory
working environment in conjunction with
the appropriate Huck Nose Assembly, to
install Huck MAGNA-LOK, MAGNA-
BULB, AUTO-BULB, C6L or MAGNA-
GRIP fasteners with a maximum diameter
of 6.35 mm (0.250").
Specifications
Installation Tool Type
LH-224 & LH-224B
Maximum recomended Air supply pressure
6.9 bar (100 psi)
Installation Tool stroke
21 mm
Installation Tool capacity
19 kN
Length (LH-224)
260 mm
Length (LH-224B)
340 mm
W idth (nominal Air Cylinder diameter)
107 mm
Height
322 mm
W eight
2.8 kg
Dimensions and weight of the Installation Tool are shown on page 5.
Noise
The sound measurement is in accordance with BS EN ISO 3746: 1996. Data is as
follows:
SEL (dBA) average
Peak(C weighted (dBA) average
W ithout Fasteners:
78.075
77.025
*Installing Fasteners:
71.975
121.425
Vibration
The vibration measurement is in accordance with BS EN 28662-1:1993. Data as follows:
* Installing Fasteners:
Aeq (m/s
2
) average = 2.458
Huck Fasteners MGP-R8-10 Pin plus MGC-U8 Collar installed in aluminium test plates
held in a workbench vice.
Disposal
Metalic and non-matilic parts/components/materials, (including any fluids), should be
disposed of by processing through authorised methods and in accordance with current
legislation.
4
Summary of Contents for LH-224
Page 2: ......