![Huawei UPS5000-S-880 kVA User Manual Download Page 97](http://html.mh-extra.com/html/huawei/ups5000-s-880-kva/ups5000-s-880-kva_user-manual_170109097.webp)
UPS5000-S-880 kVA
User Manual (CMI)
3 Installation
Issue 02 (2020-01-10)
Copyright © Huawei Technologies Co., Ltd.
89
1.
In the scenarios where holes are drilled or covers are removed for routing cables, use sealing putty to
fill in the gap between the cables and the cabinets after routing cables and checking cable
connections.
2.
After verifying the installation, reinstall all the covers.
3.
Do not remove the dustproof cover before power-on to prevent dust from entering the UPS.
Figure 3-46
Positions to be checked for foreign matter
(1) Cabinet top
(2) Wiring terminal block
(3) Switches
(4) Bottom of the cabinet
(5) Rear of the modules