Commissioning
6.1 Check Before Power-On
Table 6-1
Installation checklist
No.
Check Item
Acceptance Criteria
1
SUN2000 installation
The SUN2000 is installed correctly,
securely, and reliably.
2
Smart Dongle
The Smart Dongle is installed correctly and
securely.
3
Cable layout
Cables are routed properly as required by the
customer.
4
Cable tie
Cable ties are secured evenly and no burr
exists.
5
Grounding
The ground cable is connected correctly,
securely, and reliably.
6
Turn off the switches
The
DC SWITCH
and all the switches
connected to the SUN2000 are set to
OFF
.
7
Cable connections
The AC output power cable and DC input
power cable are connected correctly,
securely, and reliably.
8
Unused terminals and ports
Unused terminals and ports are locked by
watertight caps.
9
Installation environment
The installation space is proper, and the
installation environment is clean and tidy,