Item
Check Method
Maintenance Interval
Cable connections
Check that cables are securely
connected.
Check that cables are intact, in
particular, the parts touching the
metallic surface are not scratched.
Check that the idle COM, USB, and
AC OUTPUT ports are locked by
waterproof caps.
The first inspection is
half a year after the
initial commissioning.
From then on, perform
the inspection once six
months to a year.
Grounding
reliability
Check that ground cables are securely
connected.
The first inspection is
half a year after the
initial commissioning.
From then on, perform
the inspection once six
months to a year.
8.2 Troubleshooting
Alarm severities are defined as follows:
Major: The inverter is faulty. As a result, the output power decreases or the grid-tied
power generation is stopped.
Minor: Some components are faulty without affecting the grid-tied power generation.
Warning: The inverter works properly. The output power decreases or some authorization
functions fail due to external factors.