User Manual
iSiteC BTS3601C CDMA Base Station
System Description
Appendix B EMC Performance
B-4
Test port
Test level
Performance class
Control line, signal line
Line~line, 0.5kV
Line~ground, 1kV
B
Control line, signal line (outdoor)
Line~line, 1kV
Line~ground, 2kV
B
&
Note:
The test method is the same as IEC61000-4-5 [11].
VI. Common-mode fast transient pulse
The signal and data lines between CDMA cabinets and that connected with other
systems (such as E1 trunk line), control line and cable connected to DC input/output
port, should be the requirement for fast transient pulse anti-interference level. The
threshold value is shown in Table B-8.
Table B-8
Threshold value
Test port
Test level
Performance class
Signal control line port
0.5kV
B
DC line input/output port
1kV
B
AC line input port
2kV
B
&
Note:
Performance class A: it means that BTS can withstand the test without any damage and it can run normally
in the specified range. There is not any change in the software or data (all data in the storage or the data
being processed) related to the tested switching equipment. Equipment performance is not lowered.
Performance class B: it means that BTS can withstand the test without any damage. There is no change in
the software or the data in storage. Communication performance is lowered a little, but in the tolerance (as
defined for different products). The existing communication link is not interrupted. After the test, the
equipment can recover to the normal status before the test automatically without any interference of the
operator.
Performance class C: some functions of BTS are lost temporarily during the test, but they will recover to
normal performance in a specific period after the test (normally the shortest time needed for system
reboot). There is no physical damage or system software deterioration.
Performance class R: after the test, there is no physical damage or fault (including software corruption)
with BTS. Protection equipment damage caused by external interference signal is acceptable. When the
protection equipment is replaced and the running parameters are re-configured, the equipment can
operate normally.