FusionModule2000 Smart Modular Data Center
Installation Guide
C Installation Verification
Issue 02 (2018-03-31)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
305
C
Installation Verification
Cabinet Installation Checklist
No.
Check That
Check Result
1
The cabinets are placed according to the equipment room
layout diagram.
□ Compliant □
Incompliant
2
The height deviation of all cabinets and the depth
deviation of adjacent cabinets are less than 5 mm.
□ Compliant □
Incompliant
3
All bolts are tightened, especially the bolts used for
electric connection. Flat washers and spring washers are
installed properly.
□ Compliant □
Incompliant
4
The cabinet is clean and complies with dustproof
requirements.
□ Compliant □
Incompliant
5
The paint on the cabinet exterior is intact. If paint flakes
off, repaint that area to avoid corrosion.
□ Compliant □
Incompliant
6
The cabinet door and lock work properly.
□ Compliant □
Incompliant
7
All labels are correct, clear, and complete.
□ Compliant □
Incompliant
8
There is no foreign matter such as adhesive tape, cable
ties, paper, or packing materials left around the cabinet.
□ Compliant □
Incompliant
9
The cabinet filler panels are in proper positions so that
the cold aisle and hot aisle are isolated.
□ Compliant □
Incompliant
Aisle Containment Checklist
No.
Check Item
Check Result
1
All components of the aisle containment are installed.
□ Compliant □
Incompliant
2
The end doors can be opened and closed smoothly.
□ Compliant □