Precautions for Placing
Place cardboard boxes in sequence based on their numbers.
Figure 2-2
Arranging components
2.2 Unpacking and Acceptance
Context
Unpack and inspect all cabinets, mechanical parts, and components. Check that all the items
are intact and comply with the packing list on the presence of both the project supervisor and
customer.
Procedure
Step 1
Unpack the carton labeled
Contain Packing List
and take out the
Packing List
.
Step 2
Check all items against the
Packing List
.
Step 3
If an item is incorrect or missing, contact Huawei technical support.
Step 4
If any item is damaged, fill in the
Cargo Replacement Application Form