6 Operation and regulation
HSD S.p.A. © - 0106h03a.fm100713
69
6 Operation and regulation
6.1
Environmental conditions
The manufacturer has tested and verified its products according to environmental conditions
standard (IEC 60034-1:2006-05).Contact the manufacturer for information on potential uses in
special environments
6.2
Running-in
Prior to being packed, the product is subjected to an automatic running-in cycle to ensure the
correct distribution of lubricant (long-life grease) along the ball races of the bearings and to run-in
the balls and races of the bearings themselves. Where present, the reduction gears and servo
motors are also run-in and dynamic tests of the internal pneumatic and hydraulic circuits are
carried out.
The running-in cycle also includes a detailed check of all the control and signaling devices through
the simulation of various machining cycles on the test-bench.
6.3
Warm-up
The manufacturer uses high-precision angular contact bearing pairs, pre-loaded and lubricated for
life with special high-speed grease.
When starting-up the electrospindle for the first time each day, allow it to run a short warm-up cycle
to allow the bearings to gradually reach a uniform operating temperature and obtain uniform
expansion of the races and correct pre-loading and rigidity.
The following cycle, with a tool holder inserted and without performing
machining operations, is recommend:
50% maximum rated speed for 2 minutes;
75% maximum rated speed for 2 minutes;
100% maximum rated speed for 1 minute.
Pre-heating cycle must also be performed each time the machine is not
working for a period of time sufficient to cool the electrospindle to room
temperature.
Only in the case of the first start-up after storage or machine downtime over
four months, anticipate the pre-heating cycle by a preliminary phase of 2
minutes at 5000rpm.
Summary of Contents for ES327
Page 2: ......
Page 4: ...Information about the publication 4 HSD S p A H5801H0084 fm100713 ...
Page 46: ...3 Transport packing unpacking storage 46 HSD S p A 0103h03a fm100713 ...
Page 59: ...4 Installation and commissioning HSD S p A 0104h03a fm100713 59 ES331 ES332 1 2 4 3 1 2 4 3 ...
Page 66: ...4 Installation and commissioning 66 HSD S p A 0104h03a fm100713 ...
Page 112: ...9 Disposal of the product 112 HSD S p A 0109h03a fm100713 ...
Page 116: ...10 Troubleshooting 116 HSD S p A 0110h00a fm100713 ...
Page 121: ......