Operations 19
Install the air baffle
1.
Place the air baffle on top of the server.
2.
Install the access panel (on page
17
).
3.
Do one of the following:
o
Slide the server into the rack.
o
Install the server into the rack ("
Installing the server into the rack
" on page
26
).
4.
Connect the peripheral devices to the server.
5.
Connect the power cord to the server.
6.
Connect the power cord to the power source.
7.
Power up the server (on page
14
).
Remove the PCI riser cage
1.
Power down the server (on page
14
).
2.
Remove the power from the server:
a.
Disconnect the power cord from the power source.
b.
Disconnect the power cord from the server.
3.
Do one of the following:
o
Extend the server from the rack (on page
14
).
o
Remove the server from the rack (on page
16
).
4.
Remove the access panel (on page
17
).
5.
Disconnect all cables connected to existing expansion boards.
Summary of Contents for ProLiant DL320e Gen8 v2
Page 65: ...Cabling 65 Front I O board cabling ...
Page 94: ...Support and other resources 94 ...