Server Setup
Tower Server Optimum Environment
When installing a tower model server, select a location that meets the following
environmental standards:
•
•
•
A sturdy, level site that includes dedicated and properly grounded (earthed)
circuits, air conditioning, and ESD protection
7.6-cm (3.0-in) clearance on all sides of the tower server for proper ventilation
A separate electrical circuit for the server
CAUTION:
Protect the server from power fluctuations and temporary
interruptions with a regulating uninterruptible power supply (UPS). This device
protects the hardware from damage caused by power surges and voltage spikes
and keeps the server in operation during a power failure.
To purchase a UPS, contact a local authorized reseller or refer to the HP website
(
www.hp.com/products/ups
).
For detailed power and temperature requirements, refer to Appendix E, “Server
Specifications.”
Rack Server Optimum Environment
When installing the server in a rack, select a location that meets the environmental
standards described in this section.
Space and Airflow Requirements
To allow for servicing and adequate airflow, observe the following spatial
requirements when deciding where to install a rack:
•
•
•
Leave a minimum clearance of 63.5 cm (25 in) in front of the rack.
Leave a minimum clearance of 76.2 cm (30 in) behind the rack.
Leave a minimum clearance of 121.9 cm (48 in) from the back of the rack to the
back of another rack or row of racks.
3-2
HP ProLiant ML330 Generation 3 Server Setup and Installation Guide
HP CONFIDENTIAL
Writer: Rob Weaver File Name: d-ch3 Server Setup.doc
Codename: Flashback Part Number: 322383-001 Last Saved On: 2/11/03 1:22 PM