Installing the server into the rack
To install the server into a rack with square, round, or threaded holes, see the instructions that ship with the rack
hardware kit.
WARNING: This server is heavy. To reduce the risk of personal injury or damage to the equipment:
• Observe local occupational health and safety requirements and guidelines for manual material handling.
• Get help to lift and stabilize the product during installation or removal, especially when the product is not
fastened to the rails. Hewlett Packard Enterprise recommends that a minimum of two people are required for all
rack server installations. A third person may be required to help align the server if the server is installed higher
than chest level.
• Use caution when installing the server in or removing the server from the rack; it is unstable when not fastened
to the rails.
CAUTION: Always plan the rack installation so that the heaviest item is on the bottom of the rack. Install the
heaviest item first, and continue to populate the rack from the bottom to the top.
Procedure
1. Install the rack rail option.
For more information, see the installation instructions that ship with the selected rail system.
2. Install the server into the rack:
a. Align the inner rail of the server with the outer rail.
b. Slide the server into the rack until the quick-release latches engage with the front columns of the rack.
c. Open the latches and tighten the shipping screws, if necessary.
Removal and replacement procedures
38
Summary of Contents for HPE ProLiant DL325
Page 24: ...Customer self repair 24 ...
Page 25: ...Customer self repair 25 ...
Page 26: ...Customer self repair 26 ...
Page 61: ... SFF a Remove the optical drive cage b Remove the blank Removal and replacement procedures 61 ...
Page 136: ... Slot 2 Slot 3 Cabling 136 ...
Page 139: ... Slot 2 Slot 3 Cabling 139 ...
Page 145: ... SFF Cable routing Power supply Non hot plug power supply Cabling 145 ...
Page 149: ...Cable routing Serial port Cabling 149 ...
Page 152: ... Slot 2 Slot 3 Cabling 152 ...