2.
Assembly
2.1
Set-up, levelling
The boiler is fixed to wooden transport chocks. For trans
-
port up and down stairs, it is wise to leave these timbers
in place under the boiler.
A special foundation plate for the boiler is not an essen-
tial, but it is recommended.
Space requirement
For further information on space requirements, see chap-
ter 3.4.
The cleaning apertures must be easily acces-
sible.
Installing and levelling the boiler
Remove transport chocks. Store nuts and washers. Lift
the boiler on one side and put grub screws of boiler base
from the bottom through the slot of the boiler sockets. Fix
boiler feet using hexagonal nuts (Fig. 01).
Using a spirit level, set the boiler in longitudinal and trans-
verse direction and position it with a slight forward tilt.
This is done by adjusting the nuts on the boiler feet. After
this adjustment, the upper (locking) nuts on the boiler feet
must be tightened.
Fig. 01
7
4 217 213 / 01
ASSEMBLY