Operation
Whenever working on the machine
pay attention to the associated safety
notes in the chapter “Safety and
prevention of accidents” as well as
the accident prevention instructions!
Commissioning /
Tractor
change
During initial commissioning and when chang-
ing the tractor, the machine must be adapted
to the tractor.
In the feed pipe and associated hose assembly,
fertiliser or seed is transported from the front
hopper at the right side of the tractor to the rear
implement.
Feed pipe and hose assembly are included in the
scope of delivery and must be installed on the
tractor used. The length of the hose assembly
must be adapted accordingly.
Two feed pipes with hose assembly are installed
for an integrated double fall sluice.
1
2
3
4
5
6
Assembly parts (
ø
110 mm or 140 mm)
1 Spiral hose 0.5 m
2 Pipe elbow
3 Spiral hose 2 m
4 Pipe 2 m (2x)
5 Spiral hose 3 m
6 Guard plates for cable installation
WARNING
Danger of traffic accidents caused by improper
assembly!
¾
Have the feed pipe and hose assembly only
installed by a specialist shop.
¾
The brackets for the feed pipe must not be
mounted to a spring loaded cab. Follow the
requirements of the tractor manufacturer in
this regard.
¾
With any steering movements, the compo-
nents must not rub against other components
or interfere with the steering movements.
¾
Observe the permissible bending radii. The
hoses must not kink or become pinched with
any operating condition.
Assembly example