Installation, commissioning and operating instructions for valve-regulated stationary lead-acid batteries
7140203153 V1.4 (09.2018)
Installation, commissioning and operating instructions for valve-regulated stationary lead-acid batteries
7140203153 V1.4 (09.2018)
Table of contents
Preface
.................................................................................................................................................. 3
Symbols
.............................................................................................................................................. 4
0 Safety notices
..................................................................................................................................... 5
0.1
General Information ................................................................................................................ 5
0.2
Safety instructions for working with lead-acid batteries .............................................................. 8
1 General Information
............................................................................................................................ 12
1.1
Safety precautions .................................................................................................................. 12
1.2
Technical Data ...................................................................................................................... 12
1.2.1 Excample for single cell ......................................................................................................... 12
1.2.2 Identification plate battery ...................................................................................................... 13
1.3
CE-Mark ................................................................................................................................ 13
1.4
Disposal and recycling ........................................................................................................... 13
1.5
Service ................................................................................................................................. 13
2 Safety
............................................................................................................................................ 14
2.1
General ................................................................................................................................ 14
2.2
Personal safety equipment, protective clothing, equipment ...................................................... 14
2.3
Safety precautions ................................................................................................................ 14
2.3.1 Sulfuric acid ......................................................................................................................... 14
2.3.2 Explosive gases .................................................................................................................... 15
2.3.3 Electrostatic discharge .......................................................................................................... 16
2.3.4 Electric shock and burns ....................................................................................................... 17
3 Transport
........................................................................................................................................... 18
3.1
General ................................................................................................................................. 18
3.2
Delivery completeness and externally visible damage .............................................................. 18
3.3
Latent defects ........................................................................................................................ 19
4 Storing batteries before installation
.................................................................................................... 20
4.1
General ................................................................................................................................ 20
4.2
Storage time ......................................................................................................................... 20
4.3
Preparing for a several-month storage period .......................................................................... 20
5 Installation
....................................................................................................................................... 21
5.1
Demands on the erection site ................................................................................................ 21
5.1.1 Calculation of safety distance ................................................................................................ 23
5.2
Filling the cells ..................................................................................................................... 24
5.2.1 Check .................................................................................................................................. 24
5.2.1.1 Ventilation - preventing explosion ........................................................................................... 24
5.2.1.2 Ventilation - calculation for ventilation requirements of battery rooms ....................................... 24
5.3
Conducting an open-circuit voltage measurement .................................................................... 26
5.4
Installation tools and equipment ............................................................................................ 26
5.5
Rack Installation ................................................................................................................... 27
5.6
Cabinet Installation ............................................................................................................... 28
5.7
Handling the batteries ........................................................................................................... 29
5.8
General information on connecting the batteries ..................................................................... 29
5.9
Putting the cells/blocks into the racks ................................................................................... 30
5.10 Connecting the batteries ....................................................................................................... 32
5.10.1 Connection terminals ............................................................................................................ 32
5.10.2 Type of connection cable ....................................................................................................... 32
5.10.3 Clamping batteries using battery connectors ........................................................................... 32
5.10.4 Installing the screwed connectors .......................................................................................... 33
5.10.5 Clamping connection plates onto the batteries ....................................................................... 33
5.11 Connect the battery system to the DC power supply ................................................................ 34
5.12 Commissioning charge (initial charge) .................................................................................... 35
5.12.1 Commissioning charge with constant voltage (IU characteristic curve) ...................................... 35
5.12.2 Extended commissioning charge ............................................................................................ 35
6 Battery operation
............................................................................................................................... 36
6.1
Unloading ............................................................................................................................... 36
6.2
Charging - general ................................................................................................................... 36
6.2.1 Standby parallel operation ....................................................................................................... 38
6.2.2 Floating operation ................................................................................................................... 39
6.2.3 Switch mode operation (charge/discharge operation) ................................................................ 39
6.2.4 Float charging ......................................................................................................................... 39
6.2.5 Equalizing charge (correction charge) ........................................................................................ 40
7 Charging of HOPPECKE sun
| power
VR L
battery in Solar Applications
................................................... 42
7.1
Charge and discharge parameters ............................................................................................ 42
7.2
Alternating currents ................................................................................................................. 43
7.3
Temperature influence on battery performance and lifetime ....................................................... 43
7.3.1 Temperature influence on battery capacity ................................................................................ 44
7.3.2 Temperature influence on battery service life ............................................................................ 44
7.4
Influence of cycling on battery behaviour .................................................................................. 44
7.4.1 Endurance in cycles depending on depth of discharge ............................................................... 45
7.4.2 Endurance in cycles depending on ambient temperature ............................................................ 45
7.4.3 Electrolyte freezing point depending on depth of discharge (DoD) ............................................... 46
7.5
Remarks to warranty management ........................................................................................... 47
8 Battery maintenance
.......................................................................................................................... 47
8.1
Work to be performed every six months .................................................................................... 47
8.2
Work to be performed annullay ................................................................................................ 48
8.3
Cleaning of battery .................................................................................................................. 48
9 Testing the battery system
................................................................................................................. 49
9.1
Performing the capacity test (short form) .................................................................................. 49
9.2
Performing the capacity test (extended version) ........................................................................ 49
9.3
Capacity test of the battery ...................................................................................................... 51
10 Fault Retification
............................................................................................................................. 53
11 Required ventilation for hydrogen generated by batteries
................................................................... 53
12 Disassembly
..................................................................................................................................... 54
Inspection protocol
................................................................................................................................ 55
Safety data sheet
.................................................................................................................................. 56