Hoppecke 5 OPzV 250 Installation, Commissioning And Operating Instructions Download Page 25

48

49

Installation, commissioning and operating instructions for valve-regulated stationary lead-acid batteries
7140203153 V1.4 (09.2018)

Installation, commissioning and operating instructions for valve-regulated stationary lead-acid batteries

7140203153 V1.4 (09.2018)

9 Testing the battery system

9.1 Performing the capacity test (short form)

For tests, proceed as directed in EN 60896-21: „Stationary lead acid batteries - Part 21: Valve 
regulated types - Methods of test“ (IEC 60896-21:2004).
In addition, note special test instructions, e.g. in accordance with DIN VDE 0100–710 and DIN 
VDE 0100–718.

The following is the short form of the procedure for testing the actual capacity of your battery system. Also 
observe all instructions in 

Chap. 9.2

.

We recommend performing an equalizing charge on the battery system (as described in Chap. 
6.2.5) before performing this test.
Perform the equalizing charge no more than 7 days in advance and no less than 3 days in 
advance!

1. Make sure that all connections are clean, secure and noncorroded.
2.   During normal battery operation, measure and record the following parameters:

– Individual voltage of all cells or monobloc batteries.
– Surface temperature of at least one out of every ten cells or monobloc batteries. 
– Voltage of the complete battery system.

3.  Interrupt the connection between the battery system that you wish to test and the charger and all consumers.
4.  Prepare an adjustable load that you can connect to the battery system. 

The load current must correspond 

to the maximum permitted current for which the battery is designed.

5. Prepare a shunt that you can connect in series with the load.
6.  Prepare the voltmeter so that you can test the total voltage of the battery.
7. Connect the load, the shunt and the voltmeter. Simultaneously start a time measurement.
8.  Keep the load current constant and measure the voltage of the battery system in regular time intervals.
9.  Check the row connectors (block connectors), step connectors and tier connectors for excessive heating.
10.  Calculate the capacity of the battery system using the following formula:

Capacity (% at 20 °C) = (T

a

/T

s

) x 100

T

a

 = actual discharge time until the permitted minimum voltage is reached.

T

s

 = theoretical discharge time until the permitted minimum voltage is reached.

11.  Reconnect the battery system as originally connected and perform a boost charge 

(see Chap. 5.13)

.

9.2 Performing the capacity test (extended version)

Preparation

The best and quickest method for preparing batteries for testing is the IU charge method, also used for equa-
lizing charges. Because it is possible to exceed the permitted load voltages, appropriate measures must be 
taken, e.g. disconnection of the consumers.
The IU characteristic curve with increased voltage (2.33 - 2.40 V) x number of cells is the most common char-
ging characteristic used for commissioning the batteries.
The charge is performed with a constant voltage of max. 2.40 V/cell for up to 48 hours. The charge current 
should not be higher than 20 A per 100 Ah nominal capacity. If the elcetrolyte temperature of the cells/blocs 
exceeds the maximum of 45 °C, terminate the charge or switch to float charge to allow the temperature to drop.

8.2 Work to be performed annually

Take the following measurements and record the measurement values:
1. Voltage of the complete battery system.
2. Individual voltage of 

all

 cells or monobloc batteries.

3. Surface temperature of 

all

 cells or monobloc batteries.

4. Temperature in battery room.
5. Perform a visual check of 

all

 screwed connectors.

6. Check 

all

 screwed connectors to make sure that they are firmly secured.

7. Visual check of battery racks or battery cabinets.
8. Check to make sure that the battery room is properly ventilated and deaerated.

HOPPECKE recommends the use of a stationary battery monitoring system for the inspection of relevant data. 
Please contact your local HOPPECKE representative for further information.

8.3 Cleaning of the battery

 Danger!

Cleaning the batteries on a regular basis is necessary to maintain battery availability and to meet 
accident prevention regulations.
Batteries should be cleaned at least once per year. Note the following points:
-  While cleaning the batteries you must wear safety goggles and saftey clothes. To avoid electro-

static charges while handling the batteries your clothes, safety shoes and saftey gloves must 
have a surface resistance of <= 10^8O hm.

 Danger!

–  Do not use dry cleaning cloth!

–  Plastic parts of the batteries, especially the cell container, have to be cleaned with water or water moistened 

cleaning cloth without additives.

-  After cleaning the battery surface has to be dried with apporiate measures, like moist antistatic cleaning cloth 

(e.g. cotton).

Summary of Contents for 5 OPzV 250

Page 1: ...for valve regulated stationary lead acid batteries Installation commissioning and operating instructions Similar to the illustration...

Page 2: ...development For this reason there may be discrepancies between the product that you have purchased and the product as represented in this documentation Please keep this documentation so that it is im...

Page 3: ...ely from normal household wastes General notice or tip for better understanding and optimum use of the battery or batteries Pb 0 Safety notices 0 1 General Information Danger Incorrect use of the prod...

Page 4: ...ive counterparts of old and new names In the rest of this document old names will be listed in brackets Pb Following symbols and pictograms are pictured on each battery cell or on each battery block R...

Page 5: ...e for Maintenance Testing and Replacement of Valve Regulated Lead Acid VRLA Batteries for Stationary Applications IEEE Standard 1189 2007 Guide for Selection of Valve Regulated Lead Acid VRLA Batterie...

Page 6: ...ls blocks into the racks 30 5 10 Connecting the batteries 32 5 10 1 Connection terminals 32 5 10 2 Type of connection cable 32 5 10 3 Clamping batteries using battery connectors 32 5 10 4 Installing t...

Page 7: ...type 250 Nominal capacity C10 capacity during discharge with ten hours current I10 over a discharge time of 10 h t10 267 actual capacity C10 capacity of discharge with 10 h current 5 OPzV 250 2V 250A...

Page 8: ...ly However they contain diluted sulfuric acid H2 SO4 that is bonded in gel or glass mat The bonded sulfuric acid is extremely corrosive and can cause serious injury Further information to sulfuric aci...

Page 9: ...ic shock If a second accidental ground connection is made there is a risk of short circuit fire and explo sion If you have questions about these instructions or any other questions regarding safety wh...

Page 10: ...r is still present to make sure that your shipment is complete compare with the delivery note In particular check the number of battery pallets and the number of boxes with accessories Then inspect th...

Page 11: ...ention If the cells batteries are to be stored for a long period of time store them fully charged in a dry frost free location Avoid direct sunlight To prevent damage to the batteries an equalizing ch...

Page 12: ...cell width installation depth at least 500 mm see also IEC 62485 2 USA 36 or 915 mm HOPPECKE recommendation If possible at the installation location 1 m Otherwise in accordance with local regulations...

Page 13: ...always filled before delivery Sealed stationary lead acid battery cells must not be refilled with water during the entire battery service life Overpressure valves are used as sealing plugs These plugs...

Page 14: ...d ventilation for hydrogen generated by batteries Chap 10 Required ventilation for hydrogen generated by bat teries 5 3 Conducting an open circuit voltage measurement Before installing the batteries c...

Page 15: ...c tions mask bad cells and blocks and could cause individual battery strings to overload 2 Only batteries of the same type and same state of charge should be connected same battery type plate size and...

Page 16: ...e after another into the racks so that they are angled and level with the correct polarity Remove all transportation and hoisting equipment For large batteries it is required that you begin installati...

Page 17: ...rs must be furnished with additional insulation Avoid mechanical stress on the cell battery terminals Protect cables with large cross sections using cable ties and cable clamps The connection cables b...

Page 18: ...brations which could loosen the connection under certain cir cumstances The cables must be supported so that no mechanical load can be transferred to the connection terminals cable trays cable ducts c...

Page 19: ...n be omitted 6 1 Discharging Attention Never allow the final discharge voltage of the battery to drop below the voltage corresponding to the discharge current Unless the manufacturer has specified oth...

Page 20: ...ber of cells in series occurs after charging DC power supply Electrical Load Battery 6 2 2 Floating operation The following is characteristic for this operating mode Consumers direct current source an...

Page 21: ...on of the equalizing charge Perform the equalizing charge as follows 1 Charging with IU characteristic up to max voltage U 2 4 V cell up to 48 hours The charge current must not be higher than 20 A per...

Page 22: ...power VR L OPzV solar power OPzV bloc solar power and sun power VR M solar bloc batteries This chapter contains instructions for charging of HOPPECKE sun power VR L OPzV solar power OPzV bloc solar p...

Page 23: ...charge of 80 Fig 7 9 Endurance in cycles of sun power VR L OPzV solar power as a function of ambient temperature Cycle Number n Depth of Discharge DoD Cycles n Ambient Temperature in C 7 3 Temperature...

Page 24: ...depicts dependency of the endurance in cycles on depth of discharge and temperature Fig 7 10 Endurance in cycles of sun power VR L OPzV solar power depending on DoD and temperature 7 4 3 Electrolyte f...

Page 25: ...mum voltage is reached 11 Reconnect the battery system as originally connected and perform a boost charge see Chap 5 13 9 2 Performing the capacity test extended version Preparation The best and quick...

Page 26: ...ecting the correct discharge current or the correct discharge power Carry out the battery discharge in accordance with the regulations on performing capacity tests EN 60896 21 The discharge current an...

Page 27: ...ells The battery is on float charge at 2 25 V per cell CN Nominal capacity of the battery 200 Ah n Number of cells 2 x 30 cells fg Gas emissions factor 0 2 fs Safety factor 5 Ifloat 1 mA Ah Cell numer...

Page 28: ...w of 0 6 m3 h What factors must be considered when installing a natural ventilation system If possible the ventilation openings should be positioned on opposite walls If they must both be on the same...

Page 29: ...fire extinguishers are not suitable amongst others because of only minor efficiency possible risks or collateral damages Special protective equipment For larger stationary battery installations or lar...

Page 30: ...67 no transport as dangerous goods non spillable batteries are not subject to other requirements of IATA DGR if they meet the requirements of Special Provision A 67 Provided that poles are secured ag...

Page 31: ...correct or up to date Packing Instruction P 801 a transport as dangerous packing in accu Special Provision VV 14 transport as dangerous ADR Tunnel restriction code Note these references can be applie...

Page 32: ...on dispose with due regard to the official local regu lations 7 Handling and storage Store frost free under roof Seek agreement with local water authorities in case of larger quan tities Observe VAWS...

Page 33: ...l details in this brochure are based on state of the art technology Our products are subject to constant development We therefore reserve the right to make changes HOPPECKE Batterien GmbH Co KG P O Bo...

Reviews: