Transport and installation
HON 5020 gas pressure regulator with HON 630 pilot
38
The test setup is as follows (schematic diagram, using the two-stage HON
630
pilot with a
diaphragm assembly as a reference):
The numbers have the following meaning:
No.
Meaning
1
Inlet chamber
2
Outlet chamber
3
Inlet stop valve armature
4
Gas pressure regulator
5
Outlet stop valve armature
Proceed as follows:
Step
Description
1
Slowly close the outlet stop valve armature.
2
Apply the test medium to all detachable pipe joints.
3
Observe the test medium on all detachable pipe joints for several minutes.
If …
then …
no foam or bubbles are formed
the system is leak-proof.
the system may be put into operation.
foam or bubbles are formed
the affected pipe joint is leaking.
the system may
not
be put into operation.
Proceed with step 4.
Step
Description
4
Slowly close the inlet stop valve armature.
5
Depressurize the inlet chamber and the outlet chamber.
6
Seal the leaking pipe joints.
7
Repeat the leak test starting with step 1.
Test configuration
Checking the system for
leaks