26 | EngliSH
To connect a toilet to the SanIQ cut, proceed as follows:
The SanIQ cut features a connection in accordance with
DIN1387 / 1388 that is configured with an inlet height of
180mm. Set the toilet in front of the plastic box and slide
the toilet‘s connecting pieces into the facility‘s mounting
clamps. It is imperative to ensure that the lifting system
is not pushed in.
To connect the pressure line, proceed as follows:
To connect the pressure line, use a clamp to attach the
DN 25-pressure line at the pipe fitting, located at the top
right side of the container of the lifting system.
Sani Q one
1:50
> –
135
Backflow level
Exchange of the swing flap check valve for a ball check
valve in SaniQ one.
Unscrew the swing flap check valve with the black nut
from the container. Replace the gasket on the container
with the new gasket from the ball check valve kit. Then
insert the ball into the housing of the ball check valve and
screw it onto the container. As a last step, insert the elas-
tic transition piece onto the ball check valve and secure it
with the enclosed hose clamp.
To connect sanitation facilities (no toilet) to the side inlets,
proceed as follows:
Remove the blind cap which is screwed onto the inlet
connection and remove the black wedge-sealing ring as
well as the white pressure ring from the blind cap.
Plug the union nut (Pos. A), the pressure ring (pos. B) and
the black wedge-sealing ring (pos. C) into the DN 40 drain-
age pipe and slide it all the way into the container‘s inlet
opening.
Attach the drainage pipe by tightening the union nut
on the inlet connection. The black wedge-seal must be
between the union nut and inlet connection while you
do this. Make sure that the supply lines have a slope
towards the container (see installation examples).