October 13, 2003
is444re
Page 9 of 24
DRAFT 08/27/03
4.
Perform one of the following (see figure 2 on page 4):
•
On a vertical chase with a breaker panel (B), go to “Installing the Vertical
Chase with a Breaker Panel” on page 9.
•
On a vertical chase without a breaker panel (C), go to “Installing the Vertical
Chase without a Breaker Panel” on page 13.
Installing the Vertical Chase with a Breaker Panel
Installing the Hanger Bracket
NOTE:
Before installing a vertical chase with a breaker panel, you must install a chase hanger
bracket.
WARNING:
The installation method differs for each wall and construction type. Failure to
determine the wall and construction type could result in the collapse of the
Integris® 2001B Headwall System. Personal injury or equipment damage
could occur.
1.
Ensure that the wall meets the required specifications:
•
On non-seismic construction, make certain the walls are constructed of at least
20 gauge steel studs on 16" (41 cm) centerlines and covered with a minimum
of 5/8" (15.9 mm) dry wall.
•
On seismic construction requirements, contact Hill-Rom Technical Support at
800-445-3720.
2.
If installing a vertical chase (B) against a corner wall, allow a minimum of 1/16"
(1.6 mm) for the vertical trim between the vertical chase (B) and the side wall (see fig-
ure 5 on page 10).
3.
For the location and height of the vertical chase (B), refer to the as-built drawings.
4.
From the ceiling (Y), measure down the height of the vertical chase (B), and strike a
level horizontal line (Z).
5.
Locate the side of the vertical chase (B) on the end of raceway on the horizontal line
(Z).
6.
To locate the end of the chase hanger bracket (AA), measure 3/8" (9.5 mm) in from the
side of the vertical chase (B).
7.
Remove the chase hanger bracket (AA) from the bottom of the vertical chase (B), and
save the fasteners.
Summary of Contents for Itegris 2001B
Page 2: ......
Page 6: ...Table of Contents Page iv is444re October 13 2003 DRAFT 08 27 03 NOTES...
Page 10: ...Page 4 of 24 is444re October 13 2003 DRAFT 08 27 03 Figure 2 Component Identification...
Page 12: ...Page 6 of 24 is444re October 13 2003 DRAFT 08 27 03 Figure 3 Fasteners...
Page 14: ...Page 8 of 24 is444re October 13 2003 DRAFT 08 27 03 Figure 4 Medical Gas Drops Finished floor...
Page 24: ...Page 18 of 24 is444re October 13 2003 DRAFT 08 27 03 Figure 9 Hanger Bracket Installation...