CAUTION
!
IF EXTERIOR WALLS ARE FINISHED WITH VINYL
SIDING, IT IS NECESSARY TO INSTALL THE
VINYL PROTECTOR KIT (VPK-DV) TO THE TOP
OF THE EXTERIOR FIRESTOP FOR ALL ROUND
TERMINATION CAPS).
For Vertical Terminations -
To locate the flue and
install the flue sections:
• Locate and mark the flue centerpoint on the under-
side of the roof, and drive a nail through the center-
point.
• Make the outline of the roof hole around the center-
point nail.
• The size of the roof hole framing dimensions
depend on the pitch of the roof. There
MUST BE
a
25.4 mm clearance from the vertical flue pipe to
combustible materials.
• Mark the roof hole accordingly.
• Cover the opening of the installed flue pipes.
• Cut and frame the roof hole.
• Use framing lumber the same size as the roof
rafters and install the frame securely. Flashing
anchored to the frame must withstand heavy winds.
• Continue to install concentric flue sections up
through the roof hole and up past the roof line until
you reach the appropriate distance above the roof.
WARNING:
FOLLOW NATIONAL REGULATIONS
AND CODES OF PRACTICE FOR
MINIMUM CLEARANCES FROM GAS
TERMINALS, AND PLACEMENT OF GAS
TERMINAL.
NOTE
This also pertains to vertical flue systems installed
on the outside of the building.