4.5 Condensate Connections
•
Provision must be made for removal of condensate from the boiler and flue system.
•
Condense is mildly acidic, typically pH3
-
pH5.
•
Condense pipework must be non
-
corrosive and not copper. Hamworthy recommend
32mm dia. Plastic waste pipe. Typical volume of condensate produced is 15l/h per
100kW
•
Condense may be discharged to a standard drain subject to National or Local
regulations.
•
Location of condense pipework should prevent freezing within tundish’s, traps and
pipework.
•
The connection to the boiler condense drain accepts a straight push
-
fit coupling for
32mm i.d. plastic waste pipe.
Boiler Condensate
Connection
(32mm o/d)
Figure 4.5.2 – Boiler Condensate Connection
Open Tundish
Condense ‘U’ Trap
Minimum Fall 30mm/m
(1 in 30)
Boiler Flue
Metal sheath to protect
plastic pipe
The volume of condensate
is related to the system water
temperature and firing rate
of boiler.
Figure 4.5.1
-
Boiler Condensate Piping Installation