4.0 SITE LOCATION AND PREPARATION
4.1 Site Location.
•
The floor or plinth for the boilers and water manifold kit must be both flat and level to
ensure correct alignment of fittings and connections.
•
The floor or plinth must be sufficiently strong to support the weight of both the boilers
and manifold kit where used.
•
The floor or plinth must be fireproof in accordance with BS 6644.
•
The plantroom must have sufficient space for installation of boilers, manifold kits,
pipework, pumps controls, flues ventilation, access and servicing and other items of
plant.
4.2 Gas Supply.
•
Gas supply pipes must be in accordance with BS 6891 or IGE/UP/2
•
Gas supply connections to the boiler must not be smaller than the connection on the
boiler - Rp1”
•
Gas installation must be soundness tested to BS 6891 or IGE/UP/1 & IGE/UP/1A.
•
Gas installation must be purged to BS 6891 or IGE/UP/1 & IGE/UP/1A.
•
Inlet gas pressure to boiler nominal 20mbar (minimum 17.5mbar) dynamic at the
connection to the boiler.
•
Boiler house gas isolation valve must be clearly identified and installed close to the
entrance / exit.
Rp 1” Gas Connection
Figure 4.2 – Gas Connection Point