2.0 SUPPLY AND DELIVERY
Your boiler is despatched to site as a pre-assembled and tested unit. Each boiler is delivered by a tail lift vehicle
and lowered to ground level. It is the installers responsibility to convey the boiler to the plantroom.
The base of each boiler is specially designed to accept a standard pallet truck. This allows the boiler to be
manoeuvred into position without any pallets to remove. Additionally the boiler is designed to pass through a
standard doorway where access is restricted.
NOTE: The boiler is packaged with cardboard corner
protection and shrunk wrapped for basic protection during
handling. However, when manoeuvring the boiler care must
be taken to avoid damage to the casing.
The boiler must be kept upright during handling. Care must be
exercised to avoid toppling the boiler as this will result in
damage.