Nitrogen charging for pressure maintaining and leak detection

After the evaporator of the indoor unit is connected to the connector pipe (after welding), nitrogen more than

4.0MPa  shall  be  charged  inside  the  evaporator  and  the  piping  connected  to  evaporator  with  a  nitrogen  cylinder 
(adjusted by a reducing valve). Afterwards, the valve of the nitrogen cylinder shall be closed, for leak detection
with soapy water or leak detecting solution. The pressure shall be maintained for more than 5 minutes, and then 
whether the system pressure is reduced or not shall be observed. In case the pressure is reduced, leakage can be 
identified. After the leak point is handled, the steps above shall be repeated.  

After  the  evaporator  of  the  indoor  unit  is  connected  to  connecting  piping,  nitrogen  shall  be  charged  for 

pressure maintaining and leak detection. Afterwards, the evaporator shall be connected to the two-way stop valve 
and three-way stop valve of the outdoor unit. After the copper cap of the connecting piping is fastened, nitrogen 
more than 4.0MPa shall be charged at the access hole of the three-way stop valve with a charging hose. The valve 
of  the  nitrogen  cylinder  shall  be  closed,  for  leak  detection  with  soapy  water  or  leak  detecting  solution.  The 
pressure shall be maintained for more than 5 minutes, and then whether the system pressure is reduced or not shall 
be observed. In case the pressure is reduced, leakage can be identified. After the leak point is handled, the steps 
above shall be repeated.  

The operation above can also be completed after the indoor unit is connected to the connecting pipelines and 

the two-way stop valve and three-way stop valve of the outdoor unit, after the access hole of the outdoor unit is 
connected to the nitrogen cylinder and pressure gauge and after more than 4.0MPa nitrogen is charged. No leak 
points  are  identified  in  the  leak  detection  at  the  joint/welding  junction  of  the  indoor  unit  and  at  the  joint  of 
connecting  pipelines  of  the  two-way  stop  valve  and  three-way  stop  valve  of  the  outdoor  unit.  It  must  be 
guaranteed that each joint is available for leak detection during installation.  

The next step (vacuumizing with a vacuum pump) can only be continued after the installation steps (nitrogen 

charging for pressure maintaining and leak detection normal) are completed. 

Installation Instructions

Outdoor Unit Installation

1.

Fixation and connection

Note:

a)

Fire source shall be avoided within 3m around the place of installation.

b)

The leak detection equipment of refrigerant shall be placed at a low position in the

outdoor, and shall be opened.

1)

Fixation

The support of the outdoor unit shall be fixed onto the wall surface, and then the outdoor unit shall be fixed onto
the  support  horizontally.  In  case  the  outdoor  unit  is  wall-mounted  or  roof-mounted,  the  support  shall  be  firmly
fixed, to avoid the damage of strong wind.

2)

Installation of connecting pipes

The cone of the connecting pipes shall be aligned with the conical surface of corresponding valve connector.
The nut of connecting pipes shall be installed at a proper position and then be tightened with a spanner. Excessive
tightening torque shall be avoided, or otherwise the nut may be damaged.

Vacuumizing

A digital vacuum gauge shall be connected for vacuumizing. The duration of vacuumizing shall be at least 15

minutes, and the pressure of the vacuum gauge shall be below 60Pa.Afterwards, the vacuumizing equipment shall 
be  closed,  and  whether  the  reading  of  the  digital  vacuum  gauge  is  increased  or  not  shall  be  observed  after  the 
pressure is maintained for 5 minutes. In case no leakage is identified, the two-way stop valve and three-way stop 
valve  of  the  outdoor  unit  may  be  opened.  Finally,  the  vacuumizing  hose  connected  to  the  outdoor  unit  can  be 
disassembled.  

Leak Detection

The  joint  of  connecting  pipes  for  the  outdoor  unit  shall  be  subject  to  leak  detection  with  soap  bubble  or

dedicated leak detection equipment. 

6

Summary of Contents for 1U22KAEFRA

Page 1: ...24WADFRA 1U71WADFRA Please read this manual carefully before installation This appliance is filled with R32 Keep this operation manual for future reference 0011518288 1U09MAEFRA 1U12MAEFRA 1U18WAEFRA...

Page 2: ...nts 2 Installation Instructions 3 Relocation Procedures 8 Maintenance Instructions 9 Scrapping and Recovery 13 Indoor Outdoor Unit Installion Drawings 12 Safety Precautions 14 Read Before Installation...

Page 3: ...conditioner be sure to bleed the refrigerant circuit to ensure it is free of air and use only the specified refrigerant R32 Make sure ground connection is correct and reliable Do not earth the unit to...

Page 4: ...and open fire are not allowed around the air conditioner Transporting Management Requirements 1 The maximum transporting volume of finished products shall be determined as per local regulations 2 The...

Page 5: ...Air Conditioner Adding Extra Gas With Longer Pipe Calculator WARNING The area of the room in which R32 refrigerant air conditioner is installed cannot be less than the minimum area specified in the t...

Page 6: ...e checked first after unpacking In case the sign is raised the nitrogen sealed still exists Afterwards the black plastic seal cap at the joint of evaporator liquid pipes of the indoor unit shall be pr...

Page 7: ...Read operator manual Read technical manual Operator manual operating instructions Cotton clothes Anti static gloves BEWARE ELECTROSTATICS Goggles Electrical Safety Requirements Note 1 The surrounding...

Page 8: ...eak detection at the joint welding junction of the indoor unit and at the joint of connecting pipelines of the two way stop valve and three way stop valve of the outdoor unit It must be guaranteed tha...

Page 9: ...mount charged are recorded The refrigerant amount charged cannot be confirmed Test Run Installation Instructions 7 Please consult your reseller and or installer to determine if you have a DRED applian...

Page 10: ...r re flaring the same to the outdoor unit Relocation Procedures 8 contractor supplied line a b c d a Fix the OREO module on the board through the bayonet b Reinforce OREO module with screw c Connect c...

Page 11: ...re qualified for safety disposal of refrigerant as required in the assessment regulations 2 The equipment can only be maintained and repaired as per the method recommended by the manufacturer In case...

Page 12: ...maintenance it shall be guaranteed that the sealing functions will not be damaged or the sealing materials will not lose the function of preventing the entry of flammable gas due to aging The substit...

Page 13: ...ntamination of different refrigerants shall be avoided The total length including the refrigerant pipelines shall be shortened as much as possible to reduce the residual of refrigerant inside The cyli...

Page 14: ...shall be used as the hose and shall always be under favorable state Whether the recovery equipment is under favorable state and is properly maintained and whether all the electrical components are se...

Page 15: ...ndoor unit AIR OUTLET AIR INLET CONNECTING PIPING AND ELECTRICAL WIRING DRAIN HOSE 4 Compressor Inside of Unit 1 When installing the unit to wall roof or rooftop fix a supporter surely with nails or w...

Page 16: ...explosion will be caused fire or explosion fire or explosion fire or explosion fire or explosion fire explosion 14 Safety Precautions R32 R R3 32 2 R32 R32 R32 R32 for conventional HFC refrigerants w...

Page 17: ...R32 15 Safety Precautions WARNING CAUTION N Open the window and well ventilated the room...

Page 18: ...roof breaker for current leakage at the power source to avoid the risk of the electric shock Without a breaker for current leakage will cause risks of electric shock fire or explosion Do not use large...

Page 19: ...R32 R32 R32 R32 R32 R32 R32 R32 R32 Read Before Installation 17...

Page 20: ...3 R32 R32 R32 R32 R32 R32 R32 Read Before Installation 18...

Page 21: ...R32 R32 R32 R32 R32 R32 R32 R32 10A HFC 410A Read Before Installation 19...

Page 22: ...EFRA 1U18WAEFRA 1U50WAEFRA 1U24WAEFRA 1U71WAEFRA B 60mm B 60mm A 212mm C 126mm 51mm 51mm B 60mm B 60mm AS60QEEHRA A 218mm C 151mm 38 5mm 38 5mm AS50QDEHRA Installation Procedure 655 155 130 404 Floor...

Page 23: ...If the pipe has to be lengthened the refrigerant should be charged according to Dg m But the charge of refrigerant must be conducted by professional air conditioner engineer Before adding additional...

Page 24: ...Installation Procedure 22...

Page 25: ...evacuation degree Evacuate Installation Procedure 23...

Page 26: ...cal 4G1 0mm 4G1 0mm 3G1 5mm 3G2 5mm 1U71WADFRA Power cable 3G1 5mm2 4G1 0mm 2 POWER 1U26MADFRA 1U35MADFRA 1U53WADFRA 1U71WADFRA 4G1 0mm 7 1KW 4G1 0mm 3G2 5mm 30 2 5 25 25 20 1 POWER 1U25MAEFRA 1U35MAE...

Page 27: ...stantaneous stop F27 Directly display 8 Compressor discarging temperature protection F4 Directly display F8 Trouble record 9 Abnormal of DC motor F21 Directly display 10 Abnormal of piping sensor F7 D...

Page 28: ...our policy of continuous product improvement these dimensionsandspeci cationsmaychangeatanytime Youshouldthereforecheckwithyourdealeror Haier s Customer Care Centre to ensure this yer correctly descri...

Reviews: