CAUTION!

 

Brake linings and surfaces must always be clean and fat-free. Even very small amounts of dirt can reduce 
the braking moment considerably. 

 

14.2 

Pneumatic motor 

The pneumatic motor must be lubricated continuously by a maintenance unit. 

If not otherwise agreed, the maintenance unit must be installed by the customer. 

Should a maintenance unit be part of the consignment, the oiler must be filled with oil before the first start. 

After longer periods of standstill, gummy oil or slight rust may lead to the fact that the motors do not start at 
once or do not perform well. In most cases, this problem can be resolved by adding a few cubic meters of 
cleaning oil or paraffin into the supply hose and carrying out a test run. Afterwards, fill the same quantity of 
oil  into  the  hose  and  repeat  the  procedure  to  ensure  that  the  oil  is  well  distributed.  The  lubrication  is  then 
carried out by the oiler of the maintenance unit. 

Recommendation: 

Should longer periods of standstill be foreseen, insert some cm³ of oil into the air supply hose after the last 
use of the unit and let the motor run shortly. This will prevent corrosion. 

Lubricant: FUCHS Renolin B10 or a similar product. 

 

 

 

Use 

 

Recommendation 

 

Interval 

Maintenance unit 

 

FUCHS 

RENOLIN B10 

0,1l 

1  month 

 

 

15 

Trouble 

 

 

Please pay attention to the following in case of problems: 

  Troubles with the equipment must only be repaired by qualified personnel. 

  Secure the unit against unintended operation start. 

  Put up a warning note indicating that the unit is not to be used. 

  Secure the working area of moving parts of the unit. 

  Please read the chapter "Safety instructions". 

Notes on the repair of faults are found in the following table. 

For the repair of failures please contact our service department. 

 

 

 

   

CAUTION!

 

Trouble  caused  by  wear  or  damage  to  parts  such  as  wire  ropes,  chains,  chain  wheels,  axes,  bearings, 
brake parts, etc., must be remedied by replacing the parts with original spare parts. 

 

 

 

 

Use 

 

Recommendation 

 

Interval 

Pneumatic motor 

 

FUCHS 

RENOLIN B10 

0,1l 

3  Monate 

Summary of Contents for 32/20

Page 1: ...onorail Trolley Type 32 20 as monorail push travel trolley R as monorail hand geared trolley H as monorail electric trolley E as monorail pneumatic trolley P as swivelling Trolleys Installation Operat...

Page 2: ...Contents 1 Information 3 2 Safety 3 2 1 Warning notice and symbols 3 2 2 Duty of care of the owner 4 2 3 Requirements for the operating personnel 4 2 4 Appropriate use 5 2 5 Basic safety measures 5 3...

Page 3: ...claims require adherence to all instructions in this manual Before delivery all products are packed properly Check the goods after receipt for any damage caused during transport Report any damage imm...

Page 4: ...he device is only operated in a fault free fully functional condition and the safety components in particular are checked regularly to ensure that it is functioning properly The required personal prot...

Page 5: ...ndication label in reactor containment vessels to transport people The device is not suitable for use on stages and in studios Persons must not stand under a suspended load NOTICE If the units are not...

Page 6: ...o not throw or drop the equipment Use adequate means of transport Transport and means of transport must be suitable for the local conditions 3 2 Safety device for transport NOTICE Should a safety devi...

Page 7: ...treme environmental impact is the regular use of the equipment 4 4 Important components Wheels Machined wheels with maintenance free roller bearings Profiled wheel surfaces for the use on all standard...

Page 8: ...type leave a distance for the load hook It is important that the load hangs in the middle under the beam so that the two side plates are equally loaded The suspension eye 9 if existent for bigger load...

Page 9: ...to adjust the beam flange width dismantle the safety screws 3 at one trolley side After adjustment of dimension X and installation on the beam install the safety screws 3 again and secure them with a...

Page 10: ...nd chain Control buttons Control symbols shown are for optical information only and can vary depending on the control module Emergency stop Illustration 3 Arrow keys drive left right Illustration 4 Sy...

Page 11: ...000 kg capacity and without motor driven trolleys of hoisting unit must be tested by a qualified person before putting into operation for the first time Hoists of 1000 kg capacity and up or with more...

Page 12: ...and check the positions of the end stops 12 Maintenance 12 1 General All monitoring servicing and maintenance operations are to ensure correct functioning of the equipment they must be effected with u...

Page 13: ...crews 8 from the magnetic body clockwise 5 Tighten the locking screws 6 6 Check the air gap again and re adjust if necessary Illustration 10 13 Inspection 13 1 Periodic checks Independently from the r...

Page 14: ...the oiler of the maintenance unit Recommendation Should longer periods of standstill be foreseen insert some cm of oil into the air supply hose after the last use of the unit and let the motor run sho...

Page 15: ...be changed completely If the unit is suitable for explosive atmospheres the motor must be returned to the manufacturer for repair Air gap is too large Re adjust the air gap If the unit is suitable fo...

Page 16: ...rried out in accordance with environmental regulations 18 Additional documents 18 1 Electric wiring diagrams Electric wiring diagrams are attached to the consignment or included in the terminal box Ex...

Reviews: