16
5.52.131.00.01.09
Insert the connection cable into the connection plug without strain.
Secure lines as per VDE 0100.
9.2.2
Control line connection
Pendant with cable and plug-in connection. Plug-in before use.
Any changes of the power supply cable must only be effected by qualified personnel.
9.2.3
Power connection of the brake
The low-maintenance D.C. spring-pressure brakes are connected at the factory according to the wiring
diagram.
9.2.4
Wiring diagram
Wiring diagrams are situated in the terminal box or can be requested from HADEF by metioning of serial
number.
9.2.5
Assigning line cross-sections and fuses
Motor output
up to
kW
slow-blow
fuse
A
Cable cross-section mm
2
Cable length up to …m
1,5 2,5 4 6 10 16 25
3,9
10 58 97 155 232 388 620 969
5,9
16 36 60 97 145 242 388 606
8,4
20 29 48 77 116 194 310 485
8,9
25 23 38 62 93 155 248 388
11,9
32 18 30 48 72 121 194 303
18,5
35 16 27 44 66 110 177 277
--
50 11 19 31 46 77 124 194
--
36 9 15 24 37 61 98 154
9.3 Gear
NOTICE!
For transport, some gear types are fitted with a plug screw. Replace the plug screw by a ventilation screw
(attached) before putting the unit into operation.
9.4 Load
chain
Before commissioning the load chain must be aligned and oiled.
For the first commissioning of motorized hoists, chain oil is supplied with the delivery.
Move safety note and fixing wire away from the chain.