![GSi 21' Diameter Gamma Assembly Instructions Manual Download Page 9](http://html1.mh-extra.com/html/gsi/21-diameter-gamma/21-diameter-gamma_assembly-instructions-manual_2274962009.webp)
1. Safety
PNEG-2145
21' Diameter Gamma Roof Assembly Instructions
9
Stay Clear of Hoisted Equipment
•
Always use proper lifting or hoisting equipment when
assembling or disassembling equipment.
• Do not walk or stand under hoisted equipment.
• Always use sturdy and stable supports when needed for
installation. Not following these safety precautions creates
the risk of falling equipment, which can crush personnel and
cause serious injury or death.
ST-0047-1
Do Not Overfill the Bin
•
Do not overfill bin. Stored grain must be no higher than
the roof eaves at the outer edge.
• Filling the bin above this point creates excessive internal
pressure and can cause swelling and eventual roof
failure. The over filling of a bin can also cause the
blockage of roof vents and eaves, which will lead to a
build-up of air pressure causing roof damage.
ST-0050-1
Install and Operate Equipment Properly
•
This product is intended for the use of grain storage only. Any other
use is a misuse of the product.
ST-0057-1
Store Bin Sheets Properly
•
Sidewall bundles or sheets must be stored in a safe manner.
The safest method of storing sidewall bundles is by laying them
horizontally with the arch of the sheet upward, like a dome.
•
Sidewall sheets stored on edge must be secured so that they
cannot fall over and cause injury.
•
Use care when handling and moving sidewall bundles.
ST-0058-1