IPU-POD128 build and test guide
2) Place the IPU-M2000 onto an appropriate server lift and adjust the height such that it is suitable for the
sliders (
). If a lift is not available, this is a two person operation.
Fig. 3.28: Server lift for IPU-M2000
3) Slide the protruding inner rails into the receiving channel of the extended outer rails (
Fig. 3.29: Slide IPU-M2000 inner rails into outer rails
4) Whilst the server lift is supporting the full weight of the IPU-M2000, slide the IPU-M2000 into the extended
outer rails until you feel both sides engage a stopping mechanism (
5) Simultaneously pull on the blue tabs for the release mechanism at each side of the IPU-M2000 and then
push the IPU-M2000 unit fully into the rack (