pressure (E.S.P.), for the proper selection of heating and cooling
speeds.  The cooling blower speed is shipped set on HIGH, and
the heating blower speed is set as indicated in the Product Data
Book applicable to your model*.  These blower speeds should be
adjusted by the installer to match the installation requirements so
as to provide the correct heating temperature rise and correct cool-
ing CFM.

To adjust the circulator blower speed, proceed as follows:

1.

Turn OFF power to the furnace.

2.

Select the heating and cooling blower speeds that match
the installation requirements from the 

airflow table in the

Product Data Book

.

3.

Relocate desired motor leads  to the circulator blower heat
and cool speed terminals on the integrated control module.
(Terminals are identified as HEAT and COOL  (hot)). If heating
and cooling blower speeds are the same, a jumper wire
must be used between the heat and cool terminals.

4.

Connect all unused blower motor leads to the “PARK”
terminals on the integrated control module.  Any leads not
connected to the “PARK” terminals must be taped.

5.

Turn ON power to furnace.

6.

Verify proper temperature rise as outlined in 

Section XIV,

Startup Procedure and Adjustment - Temperature Rise

.

Orange

High

Common/Neutral

Medium Low

Circulator Blower Speeds

Low

Red

Medium Blue

Black

White

XV

XV

XV

XV

XV. NO

. NO

. NO

. NO

. NORM

RM

RM

RM

RMAL SEQUEN

AL SEQUEN

AL SEQUEN

AL SEQUEN

AL SEQUENCE O

CE O

CE O

CE O

CE OF OPERA

F OPERA

F OPERA

F OPERA

F OPERATI

TI

TI

TI

TIO

O

O

O

ON

N

N

N

N

P

OWER

 U

P

The normal power up sequence is as follows:

115 VAC power applied to furnace.

Integrated control module performs internal checks.

Integrated control module flashes LED one time.

Integrated control module monitors safety circuits
continuously.

Furnace awaits call from thermostat.

H

EATING

 M

ODE

The normal operational sequence in heating mode is as follows:

R and W thermostat contacts close, initiating a call for heat.

Integrated control module performs safety circuit checks.

Induced draft blower is energized for 15 second prepurge
period causing pressure switch contacts to close.
Humidifier terminals are energized with induced draft blower.

Igniter warm up begins after 15 second prepurge expires.

Gas valve opens at end of igniter warm up period, delivering
gas to burners and establishing flame.

Integrated control module monitors flame presence.  Gas
valve will remain open only if flame is sensed.

Circulator blower is energized on heat speed following a
fixed thirty second blower on delay.  Electronic air cleaner
terminals are energized with circulator blower.

Furnace runs, integrated control module monitors safety
circuits continuously.

R and W thermostat contacts open, completing the call for
heat.

Gas valve closes, extinguishing flame.

Induced draft blower is de-energized following a fifteen
second post purge. Humidifier terminals are de-energized.

Circulator blower is de-energized following the heat off delay
period (selectable 90, 120, 150, 180; factory set at 150).
Electronic air cleaner terminals are de-energized.

Furnace awaits next call from thermostat.

C

OOLING

 M

ODE

The normal operational sequence in cooling mode is as follows:

R and Y thermostat contacts close, initiating a call for cool.

Integrated control module performs safety circuit checks.

Outdoor fan and compressor are energized.

Circulator blower is energized on cool speed following a
fixed five second on delay.  Electronic air cleaner terminals
are energized with circulator blower.

Furnace circulator blower and outdoor cooling unit run,
integrated control module monitors safety circuits
continuously.

R and Y thermostat contacts open, completing the call for
cool.

Outdoor fan and compressor are de-energized.

Circulator blower is de-energized following a fixed forty five
second cool off delay period.  Electronic air cleaner terminals
are de-energized.

Furnace awaits next call from thermostat.

F

AN

 O

NLY

 M

ODE

The normal operational sequence in fan only mode is as follows:

R and G thermostat contacts close, initiating a call for fan.

Integrated control module performs safety circuit checks.

Circulator blower is energized on heat speed.  Electronic
air cleaner terminals are energized.

Circulator blower runs, integrated control module monitors
safety circuits continuously.

R and G thermostat contacts open, completing the call for
fan.

Circulator blower is de-energized.  Electronic air cleaner
terminals are de-energized.

Furnace awaits next call from thermostat.

XVI. OPERA

XVI. OPERA

XVI. OPERA

XVI. OPERA

XVI. OPERATI

TI

TI

TI

TIO

O

O

O

ONAL CHECK

NAL CHECK

NAL CHECK

NAL CHECK

NAL CHECKS

S

S

S

S

B

URNER

 F

LAME

The burner flames should be inspected with the burner compart-
ment door installed.  A sight glass is provided for inspection pur-
poses.  Flames should be stable, quiet, soft, and blue (dust may
cause orange tips but they must not be yellow).  Flames should
extend directly outward from the burners without curling, floating, or
lifting off.  Flames must not impinge on the sides of the heat ex-
changer firing tubes.

Summary of Contents for GMS95

Page 1: ...f in a position which is more hazardous than when the unit is in operation Remember it is your responsibility to install the product safely and to know it well enough to be able to instruct a customer...

Page 2: ...ROPER VENT FLUE AND COMBUSTION AIR PIPING PRACTICES 13 TERMINATION LOCATIONS 13 CANADIAN VENTING REQUIREMENTS 14 STANDARD FURNACE CONNECTIONS 14 ALTERNATE FURNACE CONNECTIONS 14 NON DIRECT VENT SINGLE...

Page 3: ...afety Circuit Description 31 GENERAL 31 INTEGRATED CONTROL MODULE 31 PRIMARY LIMIT 31 AUXILIARY LIMIT 31 ROLLOUT LIMIT 31 PRESSURE SWITCHES 31 FLAME SENSOR 31 XVIII Troubleshooting 31 ELECTROSTATIC DI...

Page 4: ...warranty certificate is also supplied with the unit Read the warranty carefully and note what is covered Keep the warranty cer tificate in a safe location for future reference If additional informatio...

Page 5: ...lectrical Connection Inlets Alternate 19 Coil Front Cover Pressure Tap 20 Coil Front Cover Drain Port 21 Drain Line Penetrations 22 Drain Trap 23 Blower Door Interlock Switch 24 Capacitor 25 Integrate...

Page 6: ...are set per the furnace rating plate The input rate and temperature rise are set per the furnace rating plate 100 outside air is provided for combustion air requirements during construction Temporary...

Page 7: ...ly air opening and the combustible floor Exposure to contaminated combustion air will result in safety and performance related problems Do not install the furnace where the combustion air is exposed t...

Page 8: ...g system properly vents when tested as outlined above re turn doors windows exhaust fans fireplace dampers and any other gas burning appliance to their previous conditions of use halogen type refriger...

Page 9: ...input rating of all appliances installed in that space Rooms communicating directly with the space in which the appliances are installed through openings not furnished with doors are considered a par...

Page 10: ...nsion of rectangular air ducts shall not be less than 3 inches ing shall have a minimum free area of 1 square inch per 1 000 BTU per hour of the total input rating of all gas utilization equipment in...

Page 11: ...tallation Positions figure for appropriate in stallation positions ductwork connections and resulting airflow arrangements VII HO VII HO VII HO VII HO VII HORIZO RIZO RIZO RIZO RIZONT NT NT NT NTAL AP...

Page 12: ...ane gas installations require an orifice change to compensate for the energy content difference between natural and propane gas High altitude installations may require both a pressure switch and an or...

Page 13: ...nt flue pipe and a combustion air intake pipe Refer to the appropriate section for details concerning piping size length number of elbows furnace connections and terminations MATERIALS AND JOINING MET...

Page 14: ...DIRECT VENT INSTALLATIONS On upflow units secure the combustion air intake pipe directly to the air intake coupling On counterflow units secure the combus tion air intake pipe to the air intake coupl...

Page 15: ...ue piping to the rubber elbow using a worm gear hose clamp NOTE Use of the alternate vent flue location for upright installations requires the drain trap be installed on the same side of the unit as t...

Page 16: ...ould be in stalled on either side of the wall and solvent cemented to a length of pipe connecting the two couplings The length of pipe should be the wall thickness plus the depth of the socket fitting...

Page 17: ...s in each Vent Flue Combustion Air Intake pipe Elbows and or tees used in the terminations must be included when determining the number of elbows in the piping systems If the combustion air intake pip...

Page 18: ...es If the pipes must go below the joist and then up into the last joist space to penetrate the header two 45 elbows should be used to reach the header rather than two 90 elbows VENT INTAKE TERMINATION...

Page 19: ...t installations using the standard vent flue outlet require drain hoses to be connected as follows The following quantity of hoses tubes and hose clamps are provided with the unit HOSE A QTY 1 HOSE B...

Page 20: ...flow models relocation of the front cover pressure switch hose is required Make connections as follows 1 Remove the rubber plug from the coil front cover drain port Counterflow furnaces Relocate the f...

Page 21: ...is an integral part of this furnace Field alter ation to comply with electrical codes should not be required Wires are color coded for identification purposes Refer to the wiring diagram for wire rout...

Page 22: ...at 120 VAC Turn OFF power to the furnace before installing any accessories Follow the humidifier or air cleaner manufacturers instructions for locating mounting grounding and controlling these access...

Page 23: ...field convertible for use with propane gas by replacing the regulator spring with a propane gas spring from an appropriate manufacturer s propane gas conversion kit Taps for measuring the gas supply p...

Page 24: ...rotect against external corrosion when in contact with masonry plaster or insulation or subjected to repeated wetting by liquids such as water except rain water detergents or sewage MANUAL SHUT OFF VA...

Page 25: ...nace manifold with all gas appliances in operation Maintaining proper gas pressure depends on three main factors 1 Vaporization rate depending on temperature of the liquid and wetted surface area of t...

Page 26: ...the dampers or other means used to control the flow of air must be adequate to prevent chilled air from entering the furnace and if manually operated must be equipped with means to prevent operation...

Page 27: ...nace is equipped with an ignition device which automatically lights the burner Do not try to light the burner by hand 5 Move the furnace gas valve manual control to the OFF position 6 Wait five minute...

Page 28: ...soap suds check for leaks at hose connection Bubbles forming indicate a leak SHUTOFF GASAND FIXALLLEAKS IMMEDIATELY BEFORE PROCEEDING TO NEXT STEP 6 Measure furnace gas supply pressure Supply pressure...

Page 29: ...uals the installation s gas heating value multiplied with a conversion factor hours to seconds divided by the number of seconds per cubic foot The measured input must not be greater than the input ind...

Page 30: ...sensed Circulator blower is energized on heat speed following a fixed thirty second blower on delay Electronic air cleaner terminals are energized with circulator blower Furnace runs integrated contro...

Page 31: ...DISCHARGE ESD PRECAUTIONS NOTE Discharge body s static electricity before touching unit An electrostatic discharge can adversely affect electrical components Use the following precautions during furna...

Page 32: ...e filter s by reversing the procedure for removal 4 Turn ON electrical power to furnace MEDIA AIR FILTER OR ELECTRONIC AIR CLEANER REMOVAL Follow the manufacturer s directions for service BURNERS Visu...

Page 33: ...he blower until filter clears bottom rail 5 Lower filter down and pull outward Front of Furnace Blower Front of Furnace Blower 6 Replace filter by reversing procedure X X X X XXI BEFO XI BEFO XI BEFO...

Page 34: ...34...

Page 35: ...kage proper length elbows and termination Check drain system Correct as necessary Correct pressure switch setpoint or contact motion Tighten or correct wiring connection Pressure switch hose blocked p...

Page 36: ...e sensor with emery clot See Vent Flue Pipe section for piping details See rating plate for proper gas pressure 7 7 FLASHES Flame sensor is coated oxidized Flame sensor incorrectly positioned in burne...

Page 37: ...OSTAT CONNECTIONS BU GN GND 115 VAC 24 VAC BLOWER COMPARTMENT DOOR SWITCH OPEN WHEN DOOR OPEN DOOR SWITCH WARNING DISCONNECT POWERBEFORE SERVICING WIRING TOUNITMUST BE PROPERLYPOLARIZED AND GROUNDED B...

Reviews: