17. Appendix
Pre Installation Checklist
Sr. No.
Inspection Check
Location /
Line No.
Status
1
Check Electrical Shaft size as per drawing.
Ok
Not Ok
N. A.
2
Wet riser and sprinkler should not be in the same shaft.
Ok
Not Ok
N. A.
3
Electrical Shaft Clearance for no Water seepage. Proper
plastering / white wash / tiling to avoid any seepage of
Paint / Cement on the busduct.
Ok
Not Ok
N. A.
4
Installed supports are as per approved drawing and the
supports are not at jointing section.
Ok
Not Ok
N. A.
5
Check whether all electrical equipment like transformer
/DG /Panels are positioned and as per approved drawing.
Ok
Not Ok
N. A.
6
Check the Detailed packing list with part number(s)
received, along with consignment and verify, the same
with approved drawing whether all the bus duct sections
are received. And all busduct, and its accessories are
received as per approved drawing and there is no
shortfall on accessories and hardware.
Ok
Not Ok
N. A.
7
If any shortfall of accessories or hardware are reported
the same is inform to manufacturer/supplier on the same
day.
Ok
Not Ok
N. A.
8
Busduct consignment to be stored in dry place and
covered with proper plastic.
(Do not remove the plastic
wrapped on the load / supply ends of the busduct till
taken for installation)
Ok
Not Ok
N. A.
9
Check whether all required tools and tackles mentioned in
the installation manual are available before starting the
installation.
Ok
Not Ok
N. A.
10
IR value check for every bus duct feeder before
Installation
Ok
Not Ok
N. A.
11
Client's Competent Personnel should take training on the
method of installation of the bus duct / Rising main /
Lighting Trunking from Godrej before start of installation.
Ok
Not Ok
N. A.
12
Outdoor busduct is not weather resistant, until
completely and properly installed. Should be treated
exactly the same as indoor busduct, until it is
installed.
Ok
Not Ok
N. A.
Note: - To put the Check mark for compliance.
Checked at site by:-
Name
Signature
Date
Verified by Client’s site engineer:-
Name
Signature
Date