Sketch 6B
Sketch 5A
Sketch 5C
IN
UNDER
Inside
of shower
Look from Inside
of shower
Outside
of shower
Sketch 5B
D
Base #2 is left oversized on factory and must be cut on job site.
Measure dimension “D” from end of base channel #19 to opposite wall (
Scetch 5A
). Subtract 1 ¼
from dimension “D”. The result is the exact size for Base #2. Cut Base# 2 to size.
Please Note: to obtain the best results, use a carbide tooth metal cutting chop saw or metal hack saw.
Apply a thick continuous bead of Silicone Sealant
to the underside of the Base, as shown in
SKETCH 5B.
Silicone Sealant
Base # 2
Wall Jamb
Base
Jamb Bumper
Remove 1/16” shim from under the Wall Jamb #3.
Set the Base #2 on the curb fitting it
UNDER
and
IN
wall jamb #3, as it shown on
Sketch #5C
It gap under wall jamb#3 is not big enough
for Base #2 to slide, loose the fastening Screws #12
and #26 on Wall Jamb#3 and shift it up.
When Base #2 is set, use a clean paper towel to wipe off the exes silicon from curb.
Sketch 6A
Wall Channel # 19
Base Channel #22
Set Blocks # 18
Place Setting Blocks #14 into Base Channel# 22.
Sketch # 6A
Carefully Set the Glass Panel into Wall Channel #19 and Base Channel #22.
Sketch # 6B
Be careful not to chip or strike the glass edges. Glass can brake if edges are not handled properly.