9.5.1
Fill with mortar
Fill the bore with mortar up to 4.5 cm under carriageway
level and moisten the bore wall up to the top.
Hint
Mortar sets very quickly, especially at higher temperatures
mounting adapter must be set immediately.
9.5.2
Installing the recess-mounted adapter first step
Press recess-mounted adapter with levelling jig into mortar
until 4-edge bars lie flush on floor.
Press installation conduit down into groove on both sides.
Adapter should only go about 1cm in the mortar.
Hint
Weigh down cemented adapter for flush mounting with
weight if necessary.
9.5.3
Remove levelling jig
After approx. 30 minutes of the mortar drying, unscrew the
levelling jig and place the blind chart to prevent it from get-
ting dirty.
The blind chart protects the recess-mounted adapter from
water and dirt.
9.5.4
Installing the recess-mounted adapter 2nd step
If necessary, temporarily seal the groove so that the topping
mortar cannot flow away.
Reposition mortar and cement installation box with trowel or
spatula to carriageway level.