Slimdrive SL NT product family
17
Preparation for installation
X
Then start the dielectric strength test (high-voltage test) at the test device.
Only drives which have passed the device safety test may be put into operation.
The result of the device safety test must be documented comprehensibly together with the serial number
of the drive.
After the device safety test, do not disconnect the device flat plug of the earth connection from the track.
X
Carry out the production test as described in the wiring diagram “Automatic sliding doors DCU1-NT/DCU1-2M-NT”.
6.1 Unplugging the cables
Unplugging the cables makes installation of the track on site easier.
X
Unplug the rechargeable battery cable at the control unit and secure it for transport.
X
Unplug the cable of the tooth belt locking mechanism at the control unit and secure it for transport.
X
Disconnect the transformer cable at the lustre terminal of the transformer and secure it for transport.
7
Preparation for installation
During preparation for installation the drive unit is prepared for later installation. The current drive drawing is
applicable for carrying out the installation work. All components must be identified and installed in accordance
with the drive drawing.
7.1 Processing the cover for tooth belt locking mechanism (optional)
The tooth belt locking mechanism has a locking pin which can be used to unlock or lock the tooth belt manually.
For this locking pin, a hole must be drilled on the cover in accordance with the following sketch.
The position of the hole must be checked on site. Depending on the positioning of the drive components,
minor deviations can occur here.
GEZE thus recommends only drilling the hole on site once the exact position of the tooth belt locking mecha-
nism is known.
Dimensional specifications for dimension C can be found in the machining drawing for the cover.
X
Drill a hole Ø 20 mm.
X
Deburr the hole.