INSTALLATION
Gentherm Global Power Technologies
Page 31
Figure 15 - Wiring Diagram P-5100 TEG for 12 or 24V with optional TEG Controller
Connect the customer load directly to the TEG using the following procedure. If an optional
CP interface system is applicable, then see Installation of Optional CP Interface System topic
in section 5.8.
Follow these steps to connect the customer load:
1.
Bring the customer load wires through the provided hole in the bottom of the TEG
cabinet using appropriate cable connectors for the wire or cable being used. Allow
enough wire to connect to the terminal block TB-1. See Figure 16.
2.
Connect the customer load wires to TB-1 terminals 7(+) and 8(-):
12 or 24 V: see Figure 15 if TEG Controller present.