QUICK START PROCEDURE
Gentherm Global Power Technologies
Page 3
2
QUICK START PROCEDURE
This section gives the key steps for setting up the TEG. It is for the operator who is already
familiar with operating the TEG, having successfully completed Gentherm Global Power
Technologies (GPT) TEG training course, and being a qualified service person with reasonable
knowledge and experience with industrial fuel and electrical equipment.
2.1
INSTALLATION
Follow these steps to install the TEG:
1.
Unpack the TEG from its shipping crate, keep the crate until the TEG is operational.
Locate and identify the following items that were shipped with the P-5100 TEG:
•
1 Fin Duct.
•
1 Rain Cap.
•
1 Exhaust Stack with Clamp.
•
1 Thread Sealing Compound.
•
7 Screws, #8 32 × 1/4 in. long, one spare.
•
7 Washers, #8 External Lock, one spare.
NOTE:
Inspect the TEG for damage that may have occurred during shipping. Please report
any damage as soon as possible as it may make the generator inoperable. Check
with the factory before starting a damaged TEG.
2.
Assemble the TEG as shown in Figure 3 and mount it on a firm and stable base,
sufficiently high above ground level to prevent the TEG from being inundated with
water.
3.
Connect the fuel supply to the manual shutoff valve, 1/4” FNPT, using the thread
sealant provided. Leak check the complete fuel supply system from the fuel supply
line to the burner inlet using a commercial leak detector fluid such as Snoop®.
4.
Connect the customer load:
•
connect the load to terminals 7 (+) and 8 (-);
•
C/L for CP applications connect the cathode and anode wires to the external CP
interface box.
2.2
START UP
Follow these steps to start the TEG:
1.
Ensure the battery is connected.
2.
Open the manual shutoff valve.
NOTE:
Once the TEG is started re-closing the manual shutoff valve will shut it off.