10
STEP 5 - Testing
OFF
ON
a. Turn on the electric power to the boiler. With the
boiler empty the pump should go on and the burner
must remain off.
IMPORTANT: Follow the boiler manufacturer’s start-up and operating instructions along with all applicable
codes and ordinances. Note: Water levels stated below are only for 150 psi (10.5 kg/cm
2
) operation.
This control is factory calibrated for specific applications. The following testing procedure is only meant to
serve as a verification of proper operating sequence.
Dimensions provided are typical for a boiler not being fired and/or not at pressure. Actual operating
ranges are shown on page 2 in the "Operation" section.
If the burner comes on, immediately turn the boiler off and make the
necessary corrections.
Failure to follow this warning could cause an explosion or fire and
result in property damage, personal injury or death.
!
WARNING
7
/
8
"
M
J
(22mm)
b. The boiler should begin to fill with water.
Watch the gauge glass (J) until the water
level reaches approximately
d
” (22mm)
above the horizontal cast line (M) on the low
water cut-off.
IMPORTANT: If water does not start filling the
boiler, immediately turn off the the boiler and
make the necessary corrections.
6. Re-attach the junction box cover (K).
K
Note:
Cover must be installed correctly as shown
Page 62
Summary of Contents for Lattner
Page 1: ...Instruction Manual WLF Steam Boilers 2006 to 2007 ...
Page 32: ...Page 32 ...
Page 33: ...Page 33 ...
Page 34: ...Page 34 ...
Page 35: ...Page 35 ...
Page 36: ...Page 36 ...
Page 37: ...Page 37 ...
Page 38: ...Page 38 ...
Page 39: ...Page 39 ...
Page 40: ...Page 40 ...
Page 41: ...Page 41 ...
Page 42: ...Page 42 ...
Page 43: ...Page 43 ...
Page 44: ...Page 44 ...
Page 45: ...Page 45 ...