Rev. 00 02/17
16
•
Start-up
HFF01
– Close the filler cap of the powder hopper.
4.
Set the coating parameters
Set fluidization
Powder fluidization depends on the nature of the powder, humidity and
ambient temperature. Fluidization occurs by activating the system.
1.
Connect the quick-coupling to the fluidizing air connection of the
powder hopper
2.
Set the fluidizing air at the pneumatics/fluidizing unit.
3.
Start the discharge rotors
4.
Check powder fluidization in the powder hopper
– The powder should be “cooking” slightly but regularly
CAUTION
Major dust development possible!
If fluidization is set incorrectly, the coating powder will cause a
dust cloud, which may lead to respiratory distress.
►
Set fluidization correctly.
Check that everything is working well
Start-up inspection
No
.
Inspection
✓
1
All screw connections are tight.
2
Power levels are correct. Refer to chapter on "Manually
filling the powder hopper" on Page 18.
3
Fluidization air is set correctly.
4
The interior of the powder hopper is hygienically clean.
Refer to chapter on "Cleaning the interior of the powder
hopper" on page 25.
5
The operating manual is stored with the machine close to
the work station.
6
The operator has been told that he is responsible for
instructing the personnel.
7
Assembly and installation have been concluded in
accordance with the operating manual.
8
Electrical and mechanical safety equipment is in perfect
working order.
Summary of Contents for HFF01
Page 12: ...Rev 00 02 17 12 Product description HFF01 ...
Page 14: ...Rev 00 02 17 14 Assembly Connection HFF01 ...
Page 20: ...Rev 00 02 17 20 Operation HFF01 ...
Page 26: ...Rev 00 02 17 26 Maintenance Repairs HFF01 ...
Page 30: ...Rev 00 02 17 30 Disposal HFF01 ...
Page 33: ...Rev 00 02 17 HFF01 Spare parts list 33 HFF01 Spare parts Fig 3 ...
Page 35: ...Rev 00 02 17 HFF01 Spare parts list 35 Agitator unit Fig 4 ...
Page 37: ...Rev 00 02 17 HFF01 Spare parts list 37 Agitator drive ...
Page 38: ...Rev 00 02 17 38 Spare parts list HFF01 ...
Page 42: ...Rev 00 ...