background image

              

 

 

Nuova Via di Piano Comprensorio Vulcano 

Sesto San Giovanni, MI 20099 Italy 

Tel. 02-24105.001 

 

IS 2653 GB

 

Page 

9

 of 

18

 

 

 

 

 

Figure 6 – Example of lifting hooks on main flange and on outdoor and indoor sides extremities 

 
To lift the bushing connect the crane to the central flange hooks and use a pulling device (Tirfor) to connect the 
hooks  placed  on  the  outdoor  side  flange  to  compensate  the  mass  unbalancing  (see 

Figure  7

).  Lift  carefully 

and  compensate  the  mass  unbalancing  by  acting  on  the  pulling  device  until  the  bushing  is  approximately 
horizontal. In any case, 

before lift the bushing please strictly follow the steps indicated into the provided erection 

and installation manual (IS 2654 GB).

 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Figure 7 – Example of bushing extraction and lifting

 

 

CAUTION:

 The two composite insulators are protected by a PE plastic foils. Remove the protection only after 

the installation of the bushing on the wall and just before the energizing. 
 

CAUTION:

  To  lift  the  bushing  do  not  wrap  ropes  (i.e.  ‘tie’  lifting  method)  around  the  silicone  sheds.  The 

composite insulators will be seriously damaged. 
 

CAUTION:

 It is not allowed to step on the composite insulators. The silicone sheds can be seriously damaged. 

 

CAUTION:

 The centre of gravity point is not symmetrical respect the bushing geometry. Care must be taken to 

compensate the mass unbalancing before and during the lifting operation. 
 
 

 

Outdoor side 

Indoor side 

Pulling device 

(Tirfor) 

Summary of Contents for PWS

Page 1: ...any name udated 07 07 2016 AF LP 3 Storage and transport conditions updated 22 08 2016 AF LP IS 2653 GB GE Proprietary Information Class III Confidential Export Controlled U S Government approval is r...

Page 2: ...3 Storage conditions 6 4 Technical characteristics 6 5 Bushing preparation and installation 7 5 1 Controls at the arrival 7 5 2 Bushing unpacking 8 6 Gas SF6 characteristics and gas filling instructi...

Page 3: ...oltages above 1000V 2 Safety In this document important safety requirements are highlighted by the word CAUTION and important operative instructions are evidenced by the word NOTE This manual must be...

Page 4: ...ersonnel involved in wall bushing assembly All problems detected during the bushing installation must be reported to the Foreman and to GE Grid Solutions RPV Supervisor The bushing is a pressurized de...

Page 5: ...nt of the crate during the transport it is responsibility of the transport company to carefully fix it on the vehicle by suitable retain systems like ropes synthetic pulling bands or any other method...

Page 6: ...ed and tested in accordance with the IEC 62199 and IEC 60137 standard Each section is based on A composite insulator with silicone sheds The internal shielding arrangement An internal aluminium tube c...

Page 7: ...the arrival Before proceeding with the unpacking operation it is necessary to perform the following controls Check the wooden crate status Check the external visual impact recorder s Open the crate a...

Page 8: ...upports and it is locked by locking belts Additional intermediate belts support the composite insulator to a wooden structure Figure 4 Bushing crate inside view Figure 5 Bushing inside the crate top v...

Page 9: ...ow the steps indicated into the provided erection and installation manual IS 2654 GB Figure 7 Example of bushing extraction and lifting CAUTION The two composite insulators are protected by a PE plast...

Page 10: ...ium Supplier The minimum requirement is that the characteristics will be in accordance with the data listed in the GE RPV limits column The gas filling must be performed with an equipment that prevent...

Page 11: ...e up to 0 2 MPa abs 1 bar gauge Pressure must be directly measured on the gas density monitors installed on the bushing flange Check all the gas seals for leakages with a suitable SF6 leak meter devic...

Page 12: ...the DILO machine check that the machine set up is for gas filling and that the connecting pipe is full of SF6 In the case of direct filling from the bottle check that the bottle is effectively charged...

Page 13: ...ation on the scale is expressed in MPa absolute referred to a gas temperature of 20 C This means that the instrument converts the gas density into a value of pressure referred to 20 C independently fo...

Page 14: ...pair procedure is described into the component manual see reference in the summary prepared for the specific wall bushing The composite manufacturer can provide a repairing kit and also a technical su...

Page 15: ...the camera must be properly set in order to avoid false signals and background noise In addition an infrared scan on the line terminal and the incoming cables can reveal incipient hot spots phenomenon...

Page 16: ...Gas valves electrical equipment and connecting cables When plant is off Clean the cubicle Check for gas leaks Check functionality of pressure gauge and DILO Type valves Check terminal blocks wiring ca...

Page 17: ...ect the closure cap and the fixing screws CAUTION Do not remove the closure cap and do not touch the disk when the bushing is filled with gas An explosion of the disk could be very dangerous Gas densi...

Page 18: ...lectric terminals Copper silvered Dismount and recycle Toroids Aluminium Dismount and recycle Internal electrostatic shields Aluminium Dismount and recycle Transport supports Aluminium Recycle the alu...

Reviews: