Transport and storage conditions 

 
The  bushing  is  shipped  in  a  wooden  box  suitable  for  marine  transport,

 

designed  to  provide  protection  of  the 

bushing in accordance with the specified transport conditions. 
 
The complete crate must be lifted, loaded on vehicles and transported with great care to prevent damages of 
the  bushing  or  its  accessories.  Centre  of  gravity  and  lifting  points  are  painted  on  the  crate walls, stacking of 
crates is not allowed. 
 
Shock  indicators  of  suitable  sensitivity  are  fixed  on  the  crate  walls.  They  turn  the  status  when  the  shock 
exceeds the indicator trigger level. 
 
GE Grid Solutions RPV will not respond of any damage due to un-proper operations. Removal or damage of 
the shock recorders will cause the interruption of the warranty. 
 
 
3.1 

Transport conditions 

 
The bushing can be transported by truck, ship, airplane. 
In  order  to prevent dangerous movement of the crate during the transport, it is responsibility of the transport 
company to carefully fix it on the vehicle by suitable retain systems like ropes, synthetic pulling bands or any 
other method. 
The maximum allowed transport acceleration along the three axis is 3g (29.43 m/s

2

). In case of transport by 

truck along very bad roads (‘bumpy roads) the speed must be adequately reduced to max 30 km/h. 
Trucks to be used for road transportation must have a platform of sufficient dimensions to accommodate the 
overall crate. Crate overhang from any platform and hauling are not allowed. 
 
During  the  transport  by  road  or  ship  the  good  must  be  protected  from  rain,  sea  water  and  other  exceptional 
environment conditions by tarpaulins, not provided by GE Grid Solutions RPV, suitable to full cover the crate. 
Sea transportation on the ship main deck is not allowed.  
 
3.2 

Lifting conditions 

 
The crate can be lifted by two cranes. The lifting points are indicated on the crate and are reinforced by steel 
plates (see 

Figure 1

). Lifting by fork lift is not allowed. 

 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Figure 1 – Example of two crane lifting arrangement 

 

Lifting operation must be done by qualified operators and with certified ropes and equipment. 

Summary of Contents for PWS

Page 1: ...any name udated 07 07 2016 AF LP 3 Storage and transport conditions updated 22 08 2016 AF LP IS 2653 GB GE Proprietary Information Class III Confidential Export Controlled U S Government approval is r...

Page 2: ...3 Storage conditions 6 4 Technical characteristics 6 5 Bushing preparation and installation 7 5 1 Controls at the arrival 7 5 2 Bushing unpacking 8 6 Gas SF6 characteristics and gas filling instructi...

Page 3: ...oltages above 1000V 2 Safety In this document important safety requirements are highlighted by the word CAUTION and important operative instructions are evidenced by the word NOTE This manual must be...

Page 4: ...ersonnel involved in wall bushing assembly All problems detected during the bushing installation must be reported to the Foreman and to GE Grid Solutions RPV Supervisor The bushing is a pressurized de...

Page 5: ...nt of the crate during the transport it is responsibility of the transport company to carefully fix it on the vehicle by suitable retain systems like ropes synthetic pulling bands or any other method...

Page 6: ...ed and tested in accordance with the IEC 62199 and IEC 60137 standard Each section is based on A composite insulator with silicone sheds The internal shielding arrangement An internal aluminium tube c...

Page 7: ...the arrival Before proceeding with the unpacking operation it is necessary to perform the following controls Check the wooden crate status Check the external visual impact recorder s Open the crate a...

Page 8: ...upports and it is locked by locking belts Additional intermediate belts support the composite insulator to a wooden structure Figure 4 Bushing crate inside view Figure 5 Bushing inside the crate top v...

Page 9: ...ow the steps indicated into the provided erection and installation manual IS 2654 GB Figure 7 Example of bushing extraction and lifting CAUTION The two composite insulators are protected by a PE plast...

Page 10: ...ium Supplier The minimum requirement is that the characteristics will be in accordance with the data listed in the GE RPV limits column The gas filling must be performed with an equipment that prevent...

Page 11: ...e up to 0 2 MPa abs 1 bar gauge Pressure must be directly measured on the gas density monitors installed on the bushing flange Check all the gas seals for leakages with a suitable SF6 leak meter devic...

Page 12: ...the DILO machine check that the machine set up is for gas filling and that the connecting pipe is full of SF6 In the case of direct filling from the bottle check that the bottle is effectively charged...

Page 13: ...ation on the scale is expressed in MPa absolute referred to a gas temperature of 20 C This means that the instrument converts the gas density into a value of pressure referred to 20 C independently fo...

Page 14: ...pair procedure is described into the component manual see reference in the summary prepared for the specific wall bushing The composite manufacturer can provide a repairing kit and also a technical su...

Page 15: ...the camera must be properly set in order to avoid false signals and background noise In addition an infrared scan on the line terminal and the incoming cables can reveal incipient hot spots phenomenon...

Page 16: ...Gas valves electrical equipment and connecting cables When plant is off Clean the cubicle Check for gas leaks Check functionality of pressure gauge and DILO Type valves Check terminal blocks wiring ca...

Page 17: ...ect the closure cap and the fixing screws CAUTION Do not remove the closure cap and do not touch the disk when the bushing is filled with gas An explosion of the disk could be very dangerous Gas densi...

Page 18: ...lectric terminals Copper silvered Dismount and recycle Toroids Aluminium Dismount and recycle Internal electrostatic shields Aluminium Dismount and recycle Transport supports Aluminium Recycle the alu...