background image

 

 

Instruction Manual                                                                                                                             

 

 

© GE Grid Solutions 

 

12

 

8.

 

INSPECTION BEFORE FIRST 
ENERGIZING 

 

After  putting  the  CT  in  vertical 
position,  it  is  necessary  to  wait  at 
least  48  hours  before  putting  it  in 
operation. 
 
Verify  terminals  connections  to 
assure the correct tightening torque. 

 

Verify  if  there  are  no  open-circuited 
secondary terminals. If so, they must 
be short-circuited and earthed. 

 

Verify  if  one  point  of  each  secondary 
terminal is connected to ground. 

 

Verify  the  ground  connections  of 
transformer fixation base. 

 

Verify  the  correct  position  of  the 
primary  terminal  (transformer  with 
reconnection  primary  bars).  See  set 
of drawing. 

 

Verify that the oil level indicator is in the 
green strip area. 

 

Whilst  all  care  is  taken  in  the  factory 
during  oil  filling,  the  surface  near  of 
screws  and  bellows  could  have  a  small 
quantity  of  oil.  This  shall  not  be 
considered  as  an  oil  leakage  provided 
the  bellows  are  positioned  within  the 
green strip area. 

 

It  is  not  necessary  to  remove  oil 
samples  for  analysis.  The  CT  is 
hermetically sealed 

 

If  required,  small  quantity  of  oil  can  be 
taken.  Always  verify  oil  level  indicator 
before take oil samples. 

 

Never  complete  oil  volume  without 
prior formal authorization of GE. 

 

Important remark

During 

commissioning, 

it 

is 

recommended  to  register  the  values 
acquired for each of the performed tests 
in  order  to  compare  with  future 
measurements  during  the  CT  lifetime.  
The  measurements  taken  in  the  factory 
are  important  as  so  the  measurements 
during  commissioning  of  each  CT.  The 
comparison 

between 

test 

results 

measured  at  the  field  allows  following 
the evolution of each parameter.   

 

9.

 

MAINTAINENCE AFTER ENERGIZING 

 
After installation and energizing, the CTs 
shall 

not 

require 

any 

further 

intervention.  However,  it  is  suggested 
performing  visual  inspections  during the 
first weeks of service in order to: 

 

 

Verify  the  position  of  oil  level 
indicator.  CTs  in  the  same  circuits 
shall  have  similar  oil  levels.  If  the 
indicator  is  significantly  below  or 
above 

the 

green 

level, 

in 

comparison  with  other  CTs,  it  is 
recommended 

checking 

the 

presence  of  any  of  leaking.  If 
leaking  is  found,  remove  the  CT 
from operation and inform GE; 
 

 

Verify if there is no oil leakage near 
the  fixation  base  and  secondary 
terminal box; 
 

Summary of Contents for OSKF

Page 1: ...GE Grid Solutions INSTRUCTION MANUAL 19201 CURRENT TRANSFORMER TYPE OSKF...

Page 2: ...ruction Manual GE Grid Solutions 2 GE Grid Solutions Av Nossa Senhora da Piedade 1021 37504 358 Itajub MG Brasil AIB 01 10 11 2017 RGO FML AIB 00 24 11 2013 TAA TCRP Owner revision Date Prepared Appro...

Page 3: ...STORED IN A HORIZONTAL POSITION FOR MORE THAN FOUR MONTHS IF THE TIME OF TRANSPORTION AND STORAGE EXCEEDS THIS PERIOD IT IS MANDATORY TO UNPACK AND PUT THE TRANSFORMER INTO A VERTICAL POSITION FIXING...

Page 4: ...7 3 4 Storage 9 4 BELLOWS BLOCKING SYSTEM AND ASSEMBLY IN THE STRUCTURE 9 4 1 Bellows blocking system 9 4 2 Assembly in the structure 10 5 CONTACT SURFACES PREPARATION 10 6 CONNECTIONS 10 6 1 Primary...

Page 5: ...stics of the OSKF Current Transformers For more details see set of drawings 1 Top Cover 2 Oil Level Indicator metallic bellows 3 Lifting eyes 4 Primary terminals aluminum or copper 5 Cast aluminum 6 P...

Page 6: ...th gaps OSKF may have metering and protection cores with different loads and different accuracy classes Secondary turns are evenly wound around the circumference of the ring shaped cores Changing rati...

Page 7: ...ny sign of damage or oil leakage the customer inspector or the service agent in charge of receipt shall make a written remark on shipment documents The receipt control mainly for the porcelain insulat...

Page 8: ...for the slings nylon belts reinforced and avoids blows and vibrations Follow the instructions shown in the drawing below for lifting the CT All cables or slings shall be kept in vertical position duri...

Page 9: ...is also put in place on the periphery of the bellows to protect it against contact with the top cover In order to remove the blocking system place the current transformer in vertical position on a fla...

Page 10: ...he structure If not it is necessary to insert a shim before putting the fixation screws Remove the lower lid of black plastic if applicable from secondary terminal box It is only used for transport It...

Page 11: ...g connector supplied with the equipment 6 5 Secondary terminals Connect protection and or measure instruments to the secondary terminals as shown on the nameplate See the tightening torque in drawings...

Page 12: ...sealed If required small quantity of oil can be taken Always verify oil level indicator before take oil samples Never complete oil volume without prior formal authorization of GE Important remark Duri...

Page 13: ...6 Remove the top cover to have access to the bellows and verify if there is any signal of oil leakage near the fixation of the bellows and or if the bellows is in good condition Tests It is recommend...

Page 14: ...with resin Oil disposing company properly licensed to perform such activity Oil PCB free classified as Class I hazardous residue Oil disposing company properly licensed to perform such activity Mater...

Reviews: