GE OSKF Instruction Manual Download Page 10

 

 

Instruction Manual                                                                                                                             

 

 

© GE Grid Solutions 

 

10

 

 

6)

 

Reinstall  the  Top  Cover  with  care 
lining up the vertical marker line with 
the  head  of  the  transformer  to 
ensure that original fixing position is 
maintained.    Confirm  that  the 
bellows 

is 

free 

for 

internal 

movement and in a vertical position. 
The  green  oil  level  marker  shall  be 
clearly visible through the window. 
 

7)

 

Tighten  the  fixing  screws.  The 
threads  shall  be  lubricated  with 
grease  <<  MOLYKOTE  P37>>  or 
equivalent.    The  screws  shall  be 
tightened  to  a  maximum  torque  of 
7N.m  for  screw  M6  and  16N.m  for 
screw M8. 
 

8)

 

Remove  the  lifting  eye  M10  (if 
applicable) 

 

 
 

4.2.

 

 Assembly in the structure  

 

The  transformer  shall  be  set  up  in 
vertical position. 
 
It  is  very  important  that  the  surface  on 
which  the  CT  will  be  set  up  is  flat 
(tolerance for no more than 1mm). 

Verify  if  the  four  feet  are  supported  on 
the  structure.  If  not,  it  is  necessary  to 
insert  a  shim  before  putting  the  fixation 
screws. 
 
Remove  the  lower  lid  of  black  plastic,  if 
applicable, from secondary terminal box. 
It is only used for transport. It cannot be 
used as tube guide. 
 

5.

 

CONTACT SURFACES PREPARATION 

 

It is recommended to clean all aluminum 
contact  surfaces  with  sandpaper  150 
grain  in order  to eliminate  the  oxidation 
layer.  Scrub  the  contact  surfaces  with  a 
metallic  brush  (diameter  of  the  thread 
0.3mm)  and  impregnate  with  grease  of 
the  type  “PENETROX”  or  equivalent.  All 
the surfaces must be completely covered 
with grease. 
 
For  silver  or  tinned  contacts,  only  clean 
(do  not  use  sandpaper)  and  polish  the 
side  of  the  aluminum.  Cleaning  silver  or 
tinned  surfaces  with  sandpaper  could 
cause damage to the protection layer. 

 

6.

 

CONNECTIONS 

6.1.

 

Primary Terminals 

 

Connect  the  high  voltage  cable,  or  tube, 
to 

the 

primary 

terminals 

with 

appropriate  connectors  so  that  they 
assure a good contact. 
 

 
 
 

Lifting eye M10 

Top Cover 

Cushions of 
synthetic 
foam 

Protection 
film 

Bellow 

Fix screw 

Summary of Contents for OSKF

Page 1: ...GE Grid Solutions INSTRUCTION MANUAL 19201 CURRENT TRANSFORMER TYPE OSKF...

Page 2: ...ruction Manual GE Grid Solutions 2 GE Grid Solutions Av Nossa Senhora da Piedade 1021 37504 358 Itajub MG Brasil AIB 01 10 11 2017 RGO FML AIB 00 24 11 2013 TAA TCRP Owner revision Date Prepared Appro...

Page 3: ...STORED IN A HORIZONTAL POSITION FOR MORE THAN FOUR MONTHS IF THE TIME OF TRANSPORTION AND STORAGE EXCEEDS THIS PERIOD IT IS MANDATORY TO UNPACK AND PUT THE TRANSFORMER INTO A VERTICAL POSITION FIXING...

Page 4: ...7 3 4 Storage 9 4 BELLOWS BLOCKING SYSTEM AND ASSEMBLY IN THE STRUCTURE 9 4 1 Bellows blocking system 9 4 2 Assembly in the structure 10 5 CONTACT SURFACES PREPARATION 10 6 CONNECTIONS 10 6 1 Primary...

Page 5: ...stics of the OSKF Current Transformers For more details see set of drawings 1 Top Cover 2 Oil Level Indicator metallic bellows 3 Lifting eyes 4 Primary terminals aluminum or copper 5 Cast aluminum 6 P...

Page 6: ...th gaps OSKF may have metering and protection cores with different loads and different accuracy classes Secondary turns are evenly wound around the circumference of the ring shaped cores Changing rati...

Page 7: ...ny sign of damage or oil leakage the customer inspector or the service agent in charge of receipt shall make a written remark on shipment documents The receipt control mainly for the porcelain insulat...

Page 8: ...for the slings nylon belts reinforced and avoids blows and vibrations Follow the instructions shown in the drawing below for lifting the CT All cables or slings shall be kept in vertical position duri...

Page 9: ...is also put in place on the periphery of the bellows to protect it against contact with the top cover In order to remove the blocking system place the current transformer in vertical position on a fla...

Page 10: ...he structure If not it is necessary to insert a shim before putting the fixation screws Remove the lower lid of black plastic if applicable from secondary terminal box It is only used for transport It...

Page 11: ...g connector supplied with the equipment 6 5 Secondary terminals Connect protection and or measure instruments to the secondary terminals as shown on the nameplate See the tightening torque in drawings...

Page 12: ...sealed If required small quantity of oil can be taken Always verify oil level indicator before take oil samples Never complete oil volume without prior formal authorization of GE Important remark Duri...

Page 13: ...6 Remove the top cover to have access to the bellows and verify if there is any signal of oil leakage near the fixation of the bellows and or if the bellows is in good condition Tests It is recommend...

Page 14: ...with resin Oil disposing company properly licensed to perform such activity Oil PCB free classified as Class I hazardous residue Oil disposing company properly licensed to perform such activity Mater...

Reviews: