18
END-TO-END SCHEME TESTS
This section aims to check that the signalling channel is able to transmit the ON/OFF signals used in aided
schemes between the remote line ends.
Before testing, check that the channel is healthy. For example, if a power line carrier link is being used, it may not
be possible to perform the tests until the protected circuit is in service.
18.1
AIDED SCHEME 1
Aided Scheme 1 can be tested by operating output contacts to mimic the transmission of an aided channel signal.
For these tests, an engineer needs to be present at both ends of the line - at the local end to send aided signals,
and at the remote end to observe that the signals are received. A telephone link between the two commissioning
engineers is also necessary, to allow conversation.
1.
Put the IED in test mode by setting COMMISSION TESTS > Test Mode to
Blocked
.
2.
Record which contact is assigned as the Signal Send 1 output
3.
Select this output contact as the one to test and advise the engineer at the remote end that the contact is
about to be tested.
18.1.1
PREPARATION AT REMOTE END
At the remote end, the engineer must confirm the assignment of the Monitor Bits in the COMMISSION TESTS
column in the menu, to be able to see the aided channel on arrival.
Scroll down and ensure that the Monitor Bit 1 cell is set to
DDB493
and that the Monitor Bit 5 cell is set to
DDB507
. The Test Port Status cell appropriately sets or resets the bits that now represent Aided 1 Scheme Receive
(DDB493), and Aided 2 Scheme Receive (DDB507), with the rightmost bit representing Aided Channel 1. From now
on the engineer at the remote end should monitor the indication of the Test Port Status cell.
18.1.2
PERFORMING THE TEST
1.
At the local end, set the COMMISSION TESTS > Contact Test to
Apply Test
.
2.
Reset the output relay by setting COMMISSION TESTS > Contact Test to
Remove Test
.
3.
Check with the engineer at the remote end that the Aided Channel 1 signal did change state as expected.
The Test Port Status cell should have responded as in the table below
DDB No.
507
493
Monitor Bit
8
7
6
5
4
3
2
1
Contact Test OFF
X
X
X
X
X
X
X
0
Contact Test Applied (ON)
X
X
X
X
X
X
X
1
Test OFF
X
X
X
X
X
X
X
0
X = Don't Care
Now return the IED to service by setting COMMISSION TESTS > Test Mode to
Disabled
.
18.1.3
CHANNEL CHECK IN THE OPPOSITE DIRECTION
Repeat the aided scheme 1 test procedure, but this time to check that the channel responds correctly when keyed
from the remote end. The remote end commissioning engineer should perform the contact test, with the Monitor
Option observed at the local end.
18.2
AIDED SCHEME 2
1. If applicable, repeat the test for Aided Channel 2.
P446SV
Chapter 24 - Commissioning Instructions
P446SV-TM-EN-1
655
Summary of Contents for MiCOM P40 Agile
Page 2: ......
Page 24: ...Contents P446SV xxii P446SV TM EN 1 ...
Page 33: ...CHAPTER 1 INTRODUCTION ...
Page 34: ...Chapter 1 Introduction P446SV 2 P446SV TM EN 1 ...
Page 46: ...Chapter 1 Introduction P446SV 14 P446SV TM EN 1 ...
Page 47: ...CHAPTER 2 SAFETY INFORMATION ...
Page 48: ...Chapter 2 Safety Information P446SV 16 P446SV TM EN 1 ...
Page 60: ...Chapter 2 Safety Information P446SV 28 P446SV TM EN 1 ...
Page 61: ...CHAPTER 3 HARDWARE DESIGN ...
Page 62: ...Chapter 3 Hardware Design P446SV 30 P446SV TM EN 1 ...
Page 88: ...Chapter 3 Hardware Design P446SV 56 P446SV TM EN 1 ...
Page 89: ...CHAPTER 4 SOFTWARE DESIGN ...
Page 90: ...Chapter 4 Software Design P446SV 58 P446SV TM EN 1 ...
Page 101: ...CHAPTER 5 CONFIGURATION ...
Page 102: ...Chapter 5 Configuration P446SV 70 P446SV TM EN 1 ...
Page 124: ...Chapter 5 Configuration P446SV 92 P446SV TM EN 1 ...
Page 125: ...CHAPTER 6 SAMPLED VALUE OPERATION ...
Page 126: ...Chapter 6 Sampled Value Operation P446SV 94 P446SV TM EN 1 ...
Page 136: ...Chapter 6 Sampled Value Operation P446SV 104 P446SV TM EN 1 ...
Page 137: ...CHAPTER 7 DISTANCE PROTECTION ...
Page 138: ...Chapter 7 Distance Protection P446SV 106 P446SV TM EN 1 ...
Page 196: ...Chapter 7 Distance Protection P446SV 164 P446SV TM EN 1 ...
Page 197: ...CHAPTER 8 CARRIER AIDED SCHEMES ...
Page 198: ...Chapter 8 Carrier Aided Schemes P446SV 166 P446SV TM EN 1 ...
Page 240: ...Chapter 8 Carrier Aided Schemes P446SV 208 P446SV TM EN 1 ...
Page 241: ...CHAPTER 9 NON AIDED SCHEMES ...
Page 242: ...Chapter 9 Non Aided Schemes P446SV 210 P446SV TM EN 1 ...
Page 256: ...Chapter 9 Non Aided Schemes P446SV 224 P446SV TM EN 1 ...
Page 257: ...CHAPTER 10 POWER SWING FUNCTIONS ...
Page 258: ...Chapter 10 Power Swing Functions P446SV 226 P446SV TM EN 1 ...
Page 281: ...CHAPTER 11 AUTORECLOSE ...
Page 282: ...Chapter 11 Autoreclose P446SV 250 P446SV TM EN 1 ...
Page 376: ...Chapter 11 Autoreclose P446SV 344 P446SV TM EN 1 ...
Page 377: ...CHAPTER 12 CB FAIL PROTECTION ...
Page 378: ...Chapter 12 CB Fail Protection P446SV 346 P446SV TM EN 1 ...
Page 389: ...CHAPTER 13 CURRENT PROTECTION FUNCTIONS ...
Page 390: ...Chapter 13 Current Protection Functions P446SV 358 P446SV TM EN 1 ...
Page 416: ...Chapter 13 Current Protection Functions P446SV 384 P446SV TM EN 1 ...
Page 417: ...CHAPTER 14 VOLTAGE PROTECTION FUNCTIONS ...
Page 418: ...Chapter 14 Voltage Protection Functions P446SV 386 P446SV TM EN 1 ...
Page 431: ...CHAPTER 15 FREQUENCY PROTECTION FUNCTIONS ...
Page 432: ...Chapter 15 Frequency Protection Functions P446SV 400 P446SV TM EN 1 ...
Page 438: ...Chapter 15 Frequency Protection Functions P446SV 406 P446SV TM EN 1 ...
Page 439: ...CHAPTER 16 MONITORING AND CONTROL ...
Page 440: ...Chapter 16 Monitoring and Control P446SV 408 P446SV TM EN 1 ...
Page 476: ...Chapter 16 Monitoring and Control P446SV 444 P446SV TM EN 1 ...
Page 477: ...CHAPTER 17 SUPERVISION ...
Page 478: ...Chapter 17 Supervision P446SV 446 P446SV TM EN 1 ...
Page 490: ...Chapter 17 Supervision P446SV 458 P446SV TM EN 1 ...
Page 491: ...CHAPTER 18 DIGITAL I O AND PSL CONFIGURATION ...
Page 492: ...Chapter 18 Digital I O and PSL Configuration P446SV 460 P446SV TM EN 1 ...
Page 504: ...Chapter 18 Digital I O and PSL Configuration P446SV 472 P446SV TM EN 1 ...
Page 505: ...CHAPTER 19 FIBRE TELEPROTECTION ...
Page 506: ...Chapter 19 Fibre Teleprotection P446SV 474 P446SV TM EN 1 ...
Page 522: ...Chapter 19 Fibre Teleprotection P446SV 490 P446SV TM EN 1 ...
Page 523: ...CHAPTER 20 ELECTRICAL TELEPROTECTION ...
Page 524: ...Chapter 20 Electrical Teleprotection P446SV 492 P446SV TM EN 1 ...
Page 534: ...Chapter 20 Electrical Teleprotection P446SV 502 P446SV TM EN 1 ...
Page 535: ...CHAPTER 21 COMMUNICATIONS ...
Page 536: ...Chapter 21 Communications P446SV 504 P446SV TM EN 1 ...
Page 606: ...Chapter 21 Communications P446SV 574 P446SV TM EN 1 ...
Page 607: ...CHAPTER 22 CYBER SECURITY ...
Page 608: ...Chapter 22 Cyber Security P446SV 576 P446SV TM EN 1 ...
Page 625: ...CHAPTER 23 INSTALLATION ...
Page 626: ...Chapter 23 Installation P446SV 594 P446SV TM EN 1 ...
Page 637: ...CHAPTER 24 COMMISSIONING INSTRUCTIONS ...
Page 638: ...Chapter 24 Commissioning Instructions P446SV 606 P446SV TM EN 1 ...
Page 695: ...CHAPTER 25 MAINTENANCE AND TROUBLESHOOTING ...
Page 696: ...Chapter 25 Maintenance and Troubleshooting P446SV 664 P446SV TM EN 1 ...
Page 712: ...Chapter 25 Maintenance and Troubleshooting P446SV 680 P446SV TM EN 1 ...
Page 713: ...CHAPTER 26 TECHNICAL SPECIFICATIONS ...
Page 714: ...Chapter 26 Technical Specifications P446SV 682 P446SV TM EN 1 ...
Page 741: ...APPENDIX A ORDERING OPTIONS ...
Page 742: ...Appendix A Ordering Options P446SV P446SV TM EN 1 ...
Page 744: ...Appendix A Ordering Options P446SV A2 P446SV TM EN 1 ...
Page 745: ...APPENDIX B SETTINGS AND SIGNALS ...
Page 746: ...Appendix B Settings and Signals P446SV P446SV TM EN 1 ...
Page 954: ...Appendix B Settings and Signals P446SV B208 P446SV TM EN 1 ...
Page 955: ...APPENDIX C WIRING DIAGRAMS ...
Page 956: ...Appendix C Wiring Diagrams P446SV P446SV TM EN 1 ...
Page 960: ......
Page 961: ......