Chapter 2. Setup and Operation
8
MG-101 User’s Manuall
2.2 Operating Procedure
To operate the MG-101, refer to
below and
to complete the following steps:
1.
Fully close
all four rotameter valves by turning them clockwise.
2.
Set the
WET/DRY
selector valve to
DRY
.
CAUTION!
This valve must always be in the WET position before the “WET GAS” flowmeter valve is opened,
and it must remain in the DRY position until the “WET GAS” flowmeter valve is closed.
3.
Set the pressure regulator on the nitrogen gas inlet line to approximately 55 psig.
4.
Make sure the vent valve at the top of the front panel is
fully
open.
5.
Fully
open the valve on the
WET GAS DILUTED
rotameter.
Note:
The rotameters are dual-range, floating-ball types, each having both a steel ball and a glass ball. When
reading the rotameters be careful to watch either the steel ball or the glass ball (see Figure 4 below) as
directed (numbers in tables are followed by an
S
or a
G
to designate the ball material).
Figure 5: Rotameter Valve and Balls
Glass Ball (black)
Steel Ball (silver)
Valve
Summary of Contents for MG-101
Page 1: ...GE Measurement Control Moisture 910 115 Rev E March 2012 MG 101 User s Manual ...
Page 2: ......
Page 4: ...ii no content intended for this page ...
Page 8: ...Contents vi MG 101 User s Manual no content intended for this page ...
Page 12: ...Chapter 1 General Information 4 MG 101 User s Manual no content intended for this page ...
Page 22: ...Chapter 2 Setup and Operation 14 MG 101 User s Manual no content intended for this page ...
Page 32: ...Warranty 24 MG 101 User s Manual no content intended for this page ...
Page 33: ......