Chapter 8 Replacement Procedures
8 - 417
8-16-6
Patient I/O ECG Option replacement
Table 8-412 Manpower / Time and Tools
Manpower /
Time
Tools / PPE
One person /
30 minutes,
excludes travel
8-2-5 "Tools needed for servicing the LOGIQ E10" on page 8-6
/
8-2-6 "PPE Required During Service" on page 8-6
Table 8-413 Preparations and Preparation Links
Preparations - you must perform the following steps
WARNING
WARNING
Risk of electrical shock, system must be turned off. Avoid all contact with electrical contacts,
conductors and components. Always use non-conductive handles designed for the removal
and replacement of ESD sensitive parts. All parts that have the potential for storing energy
must be discharged or isolated before making contact.
IF THE SHEAR WAVE OPTION IS PRESENT, MAKE SURE THE LEDS ON THE CAPACITOR
PACK ARE OFF BEFORE REMOVING THE CAPACITOR PACK.
WARNING
WARNING
DO NOT TOUCH ANY BOARDS WITH INTEGRATED CIRCUITS PRIOR TO TAKING THE
NECESSARY ESD PRECAUTIONS.
1. ALWAYS CONNECT YOURSELF. THE ESD WRIST STRAP SHOULD BE
CONNECTED TO ONE OF THE TWO RECEPTICALS INTEGRATED ON THE FRAME,
SPECIFICALLY FOR THAT PURPOSE.
2. FOLLOW GENERAL GUIDELINES FOR HANDLING OF ELECTROSTATIC SENSITIVE
EQUIPMENT.
WARNING
WARNING
Energy Control and Power Lockout for LOGIQ E10
:
When servicing parts of the Ultrasound System where there is exposure to voltage greater than 30
Volts:
1. TURN OFF THE SCANNER.
2. UNPLUG THE SYSTEM.
3. MAINTAIN CONTROL OF THE SYSTEM POWER PLUG.
4. WAIT FOR AT LEAST 20 SECONDS FOR CAPACITORS TO DISCHARGE AND THE ON/OFF
BUTTON (WHITE LIGHT ON THE OP PANEL) TO TURN OFF, AS THERE ARE NO TEST POINTS
TO VERIFY ISOLATION.
5. REMOVE THE BATTERY COVER AND DISCONNECT THE POWER CABLES
J10
and
J11
(black
and red) FROM THE BACKPLANE. See:
and
.
Beware that the Main Power Supply, the Batteries, Power Module, ECB Shear Wave Capacitor Pack
may be energized, even if the power is turned OFF if the cord is still plugged into the AC Outlet.
1. Power down the system.
2. Disconnect the mains power cable from the wall outlet and all Probes.
3. Remove the Left Side Cover, the Battery Cover and the Front Cover. Remove the Shear Wave Option, if present.
Preparation Links (if you need more information):
• 4-2-4 "Power SHUT DOWN" on page 4-9.
• 8-6-3 "Side Cover(s)/Side Air Intake (Filter) inspection / replacement" on page 8-33.
• 8-6-4 "Front Cover replacement" on page 8-38.
• 8-16-9 "Shear Wave Option replacement" on page 8-431
, if the Shear Wave Option is present.
Signed
Date
TAG
&
LOCKOUT
J10
J11
J10
J11
Signed
Date
TAG
&
LOCKOUT
Summary of Contents for LOGIQ E10
Page 1: ...LOGIQ E10 Basic Service Manual 5750007 1EN Rev 1 Version R1 2018 GENERAL ELECTRIC COMPANY...
Page 2: ......
Page 4: ...DIRECTION 5750007 1EN REVISION REV 1 LOGIQ E10 BASIC SERVICE MANUAL ii...
Page 5: ...DIRECTION 5750007 1EN REV 1 LOGIQ E10 BASIC SERVICE MANUAL iii...
Page 6: ...DIRECTION 5750007 1EN REVISION REV 1 LOGIQ E10 BASIC SERVICE MANUAL iv...
Page 7: ...DIRECTION 5750007 1EN REV 1 LOGIQ E10 BASIC SERVICE MANUAL v...
Page 8: ...DIRECTION 5750007 1EN REVISION REV 1 LOGIQ E10 BASIC SERVICE MANUAL vi...
Page 9: ...DIRECTION 5750007 1EN REV 1 LOGIQ E10 BASIC SERVICE MANUAL vii...
Page 10: ...DIRECTION 5750007 1EN REVISION REV 1 LOGIQ E10 BASIC SERVICE MANUAL viii...
Page 11: ...DIRECTION 5750007 1EN REV 1 LOGIQ E10 BASIC SERVICE MANUAL ix...
Page 12: ...DIRECTION 5750007 1EN REVISION REV 1 LOGIQ E10 BASIC SERVICE MANUAL x...
Page 13: ...DIRECTION 5750007 1EN REV 1 LOGIQ E10 BASIC SERVICE MANUAL xi...
Page 14: ...DIRECTION 5750007 1EN REVISION REV 1 LOGIQ E10 BASIC SERVICE MANUAL xii...
Page 34: ...DIRECTION 5750007 1EN REV 1 LOGIQ E10 BASIC SERVICE MANUAL xxxii Hardware Kit 9 49...
Page 776: ...DIRECTION 5750007 1EN REV 1 LOGIQ E10 BASIC SERVICE MANUAL Index 4...
Page 777: ......