3. Draw a line on the floor through the isocenter perpendicular to the isocenter line.
4. Locate the appropriate template based on your system configuration per Table 1. Place the
template over the isocenter lines.
Table 1-1:
SYSTEM CONFIGURATION
TEMPLATE
Gantry with Omega Angio Table
2127792
Gantry with Innova
IQ
Table
2360133
Base plate for Innova
IQ
Table add-on
2361993
NOTE:
Determine the position of the reinforcement bars in the concrete floor so the anchor
holes will not run into them. The template can be slightly adjusted about the cable exit
hole isocenter to accommodate the rebar positioning. Be sure to shift the isocenter line,
if necessary, to accommodate positioning the Omega/Innova
IQ
Table.
5. Mark the bolt hole locations for the Gantry and table base plates with a punch and hammer.
6. Scribe lines on the floor at 0, 90, 180, and 270 degrees about the isocenter as shown in
7. Drill the mounting bolt pilot holes (using 3/8” drill).
1.5 Finalization
No finalization steps.
Single Plane and Biplane Innova Systems Pre–Installation Kit Installation Procedures
GE Healthcare
Direction 2290880-12-1EN, Revision 1
Chapter 1 Installation Procedure
19
Summary of Contents for Innova Series
Page 53: ......