Installation procedure:
1. Please refer to figure 6 in chapter 4.1 and drawing “TERMINALS” for the location of terminals.
2. Remove the rear grid by loosening the 4 screws.
3. Remove the middle front panel that covers the MCB-switches.
Hold the panel at both sides and pull firmly.
4. Remove the lower front panel that covers the battery drawers. Lift the panel and pull.
5. The input terminals are mounted at the rear side of the UPS.
Connect the mains supply wires to the terminals 7 (L1), 8 (L2), 9 (L3) and 10 (Neutral) and the
earth wire to the EARTH terminal.
6. Connect the load wires to the terminals 1 (Line) and 2 (Neutral) and the earth wire to the EARTH
terminal (3).
7. Connect the bypass supply wires to the terminals 4 (L1) and 5(N) and the earth wire to the
EARTH terminal (6).
8. Use the clamps that came with the unit to attach the wires to the rear of the cabinet.
Position the clamps in the slots (20, see fig. 6).
9. If you want to install battery extension packs proceed with step 10.
If you are not using battery extension packs skip to step 19.
10. Please refer to drawing “BATT. PACK CONNECTION”.
Battery extension pack(s) are shipped with all materials necessary to connect them to the UPS
(see chapter 3.1).
The pack(s) can be connected to the terminals at the rear panel of the UPS.
The internal DC wires are already connected to the rear terminals 12,14 (plus) and 13,15
(minus).
11. Be sure that all MCBs are in OFF position.
12. Be sure that the mains supply voltage and the bypass voltage are not present on the input
terminals.
13. Make sure that all battery fuses at the front of the cabinet are removed.
14. Use a voltmeter to check that there is no DC voltage between terminals 12 and 13 and between
terminals 14 and 15.
15. Make sure that all battery fuses of the battery cabinet are removed.
16. First install the left plus (red) and minus (black) wire of the battery cabinet to the left plus and
minus of the UPS (terminals 12 and 13).
Then install the right plus (red) and minus (black) to the right plus and minus of the UPS
(terminals 14 and 15).
17. Install all battery fuses at the front of the battery cabinet and in the front of the UPS.