The Atlas Fuel System
Site Preparation
Page 3-10
MDE-4363G Atlas™ Fuel Systems Owner’s Manual · August 2018
Site Preparation
To ensure safety and long-term reliability of your equipment, ensure that your units are
installed by a knowledgeable Authorized Service Contractor (ASC). When your units are
installed, ensure that the installer considers the guidelines in the following section.
Important Requirements for E85 Units
The following equipment and materials are required to properly install E85 units:
UL-listed E85 Hose (Q13486)
• Veyance
SM
Flexsteel
®
Futura
™
Ethan-All for E85
• Veyance Flexsteel Futura for E25
Note: Extended Reach hoses are not available for the E85 applications.
UL-listed E85 Nozzle (M11298)
OPW 21GE
Note: Approved for use with the E85 dispensers, as required under UL 87A.
UL-listed E85 Swivel (N23748-04)
OPW 241 TPS-0492
Note: Approved for use with E85 dispensers, as required under UL 87A.
UL-listed E85 Shear Valve (T19695-23)
OPW 10P-0152E85
Note: Approved for use with E85 dispensers, as required under UL 87A.
UL-listed E85 Breakaway (N23010-10)
OPW 66V-0492
Note: Approved for use with E85 dispensers, as required under UL 87A.
Filter
Use only filters specifically marked for use with E85.
UL-listed Pipe Sealant
Use only UL-listed TPS PTFE Pipe Sealant manufactured by SAF-T-LOC International Corp.
UL-listed Teflon
®
Tape
Use only UL-listed Taega Technologies Inc. Teflon tape.
Note: Teflon tape must be used only at the inlet pipe connection.
For E85 Front Load units, side B is the side with the Junction Box. For nozzle boot
positioning for the different models, refer to Atlas Foundation Diagrams section in
MDE-4331 Atlas Fuel Systems Installation Manual.
IMPORTANT INFORMATION