MDE-4813D CFN PLUS Installation Manual · February 2018
27
2-6.3.1. LAN Cable Routing
Due to Federal Communications Commission (FCC) requirements, the LAN cable entering the
system box should be exposed (near the entry point, inside the box), and the exposed shielded wire
of the cable must be connected to the nearest ground point on the bottom plate. Use only LAN cable
with RJ-45 metal connector connected to the shield.
2
2
-
-
7
7
.
.
P
P
O
O
W
W
E
E
R
R
S
S
E
E
T
T
U
U
P
P
2-7.1. General
The power equipment shall be installed in the Main Power Cabinet of the station office. It should
include the following:
•
Mains Circuit Control Box (MCC)
•
Uninterruptible Power Supply (UPS) - Online (“True”) UPS
•
Power Distribution Box (PDB)
shows the requested connections of the power equipment.
Figure 2-5 Power Equipment Connections
Beside the power equipment, other components shall be connected to the power supply such as the
TLG and the dispensers.
2-7.2. Power Distribution and Grounding
Installation of CFN PLUS in station with mechanical pump requires specific power distribution and
grounding as shown in
Installation of CFN PLUS in station with electronic pump requires specific power distribution and
grounding as shown in